HomeMy WebLinkAbout2002-03-25 02-160 ORDERDate: 3-25-02
Item/Subject Order, Authorizing the Execution of a Cost Sharing Agreement with the Air National
Guard for Runway Improvements.
Responsible Deparbnent: Airport
Commentary:
Improvements m the runway are being funded with Airport Improvement Project Ponds, State
Department of Transportation Funds, Airport Funds, and Air National Guard Funds. This order will
allow the City Manager to enter into a cost sharing agreement with the Guard for this project. For
this federal Oscal year, the Guard has allocated $5,000,000 for this project.
Legal Approval
ry Solicitor
Introduced for
X_ Passage
_ First Reading Page_ of
Referral
Rebecca Hupp
Department Head
Manager's Comments:
Recommend approval.
z Ail e //
Oty Manager
Associated Information: Order
Budget Approval:
,4 4LLA
Finance DlreRer
Legal Approval
ry Solicitor
Introduced for
X_ Passage
_ First Reading Page_ of
Referral
02-160
qq'.¢ Assi6ndto Councilor Bohnan March 25. 2002
$•a
CITY OF BANGOR
(=LE.) Order, AuthwRing the Execution of a Cos[ sharing Agreement with the Air National Guard for
Runway ][rnprovements.
WHEREAS, the runway at Bangor International Airport Is in need of Improvements; and
WHEREAS, part of the funding for this project is from Federal Airport Improvement Project unds and
Maine Department of Transportation Funds; and
WHEREAS, the Air National Guard will assist in funding a portion of the improvements.
NOW, THEREFORE, BE R ORDERED BY THE QTY COUNCIL OF THE QTY OF BANGOR, THAT:
The City Manager is hereby aultorhM to execuUe a ces[ shadrlg agreement AM Me Air National
Guard for runway improvements at Bangor Intemadonal Airport, a copy of which B attached W this
order.
IN Cres muNCIL "^5
Marro 25, xooz 02-160
Morton Made and seeoaded
for Passage ORDER
Passel
.,Ll,. . �m LLLt 11 Title,Awthoriting the Nxaantfon of a Cast
MHPPfy ClIT CLERK sharing Agreement with the Air National
Guard for Anmay Improvements
Assigned to
Councllor
✓V tt9-�
Page 2
02-160
TBCUNTCAL APPENDIX A
tY Ice `.WI
CITY OFBANGOR CONSTRUCTION
1. Purptae. This Statement of Work defines the City or Bangm,s obligation to providing
local construction.
2. Scope of Responsibilities and Administration.
2.1. Upon acceptance of the Project Design Documents, the City of Bangorwill contract
for the eonstmcdun of the project according to this MCCA.
2.2. The City of Bangor shall carry out the construction of the Project in strict aecuvl rmt
with the Pmject Design Documents.
2.3. NUB Approval of C nsrm min Documents. Unless audsotity is delegated, the
City of Bangor shall pmvlde any professed contract(s) for construction of the Project to
NGB for its review, comment, and approval prior to the City of Bangor's execution of the
commit. By formal written notice, NOR shall provide the City of Bangor with ib
ummants, approval or disapproval withie 30 days of its receipt of the proposed City of
Bangor eantmet(s). NOS may disapprove the courwatfs) only for the following rcas im:
2.3.1. The contract price exceeds the amount in the finance plan for construction in this
Appendix; or.
231, The proposed contractor has been debauW or suspended front performing Federal
comment or performing cuntmem under Godds or Cooperative Agm meards with the
Federal Government.
24. Inspection and Acceptance of Construction.
2.4.1. The City of Bangor shall be responsible for inspection and acceptance or the work
by its conumetien confretor(s). ANG shall ria issue directions to any City of Bangor
connector and shall communicate with a City of Bangor contractor only through, or with
the permission of, an authorized City of Bangor representative,
2.4.2. Upon the USPFO's concurrence with final acceptance, the project shal I he
considered couples.
2.4.3. Final payment shall be after the final Project Inspection Repun, as defined below,
has been completed and then approved by the USPFO.
Page 3
02-360
Project Final Inspection Report
PROJECT: [P jot Number am Title]
1. Some: [Smeor Temtoryl City: [Bax]
This duplicates baae" information covered later on the form.
2. Date: [Day, Month, Your] Percent Completed: (XX%I
3. Contracting ORiar: [Name)
a. Contractor: [Name of Companyl
5. Contract No.: (Complete Contract Number] Amounm [Total Conrraot Cost]
6. Base: (4warion of completed project]
This is to certify Wet [Company], connector, completed on [date] all work under Contr et
No. [common number) dated (contract date] for Project [Project number and pnjjoet title]
at (Baso, Sum or Territory); that fiord inspection of the work was accomplished by We
undersigned on (dotel; that the materials and labor wave Armistead! in accordance with the
rorrun of the specifications and mouser; that all required guarentas haw been fumished;
that the work was performed in accordance with approved specifications and/or contract
drawings as modified by approved change orders and supplemental agreements with no
exceptions; and that all work under this contrw:t was completed on [date].
[Project lnspectorl
The work completed under this contract is hereby accepted tot the Govemmmt as
of lintel.
lt.mu-neungtnuceq
3. Project Finance Plant:.
3.1. The prcjar Bnonce plan is the maximum amount for which NOB is obligated at
mimbutse the City of Bangor for the crista of performance of this MCCA. The amount of
my projeet finance plan line item cost Bmiiation shell not be excadcd.
3.2. Unless otherwise provided for W the project Bnonce plan, any line item themin may
be changed only by amendment of this MCCA. Either party may propose a change to a
finmrm plan by submitting each proposal in writing to the other party. Use NGR 5-
UANGI63-101, Appendix E, Cooperative Agmement Modification Form or Standard
point 30.
Page 6
02-160
PROJECT CONSTRUCTION FINANCE PLAN
FKNN99D71 Repair Airfield pavements, RIA
ESTIMATED COST OF CONSTRUCTION: $15,825,000
nnivity
Paumuud
ANG$hare
Eetimawd
myShote
Gatl�wLLvl
Warshaw
P timuwd
'fowl
Cunsa0nionafCort$ketetl lmpmwmem
$1.9804000
$ 650.000
$8,770"
$14,00O"
p�wuwtinn ofANOlnOnuvcmcnw
$ 0$
0$
o
S 0
Cuwlnxtiunurf]ty 4nquwmeMn
$ 0
$ 0
$ 0
$ 0
(tnwwctimSupervleitm
$ 250vW0
$ 3504*01
$ 0
$ GMWn
Tnmle
$O,bW.UW
$1,000,00)
$fl,]JO,IM
$I4,61)0,000
Project Construction Finmme Plan Nutea, Termx and Conditions:
1. This Project Construction Finatme Plan is incorporated into this Appendix four die
porpaee of identifying ahnml costs.
2. The ANGshare indiceredis only sportiest of the acWalrequired funding. "line
estimated total scope ofthoprojectis$19,2(f),000. The estitasted ANG share of this
project would be $9,250,000 if ull required work is completed. The City of Burger is
limited to the funds available ($4,830,000) when considering which portions or work W
award.
PROJECT DESCRIPTION, SCOPE, AM SCHEDULE
PROJECTDESCRIPIION
Repair airfield pavemmtm Ihmugh a mories of wmcrale reconstruction and overlay with
blWmlllnll5 pavement. Change the width of the runway form 300' W 2f10'. Replace
runway and taxiway electrical systems. P ject will be phased over two years.
PROJECT SCOPE
This project includes reconstruction and bimnunous overlay of an 11,440' % 20u,
toneless runway. The existing runway is 300' wide requiring the airfield lighting an be
relocated The entire nrnway light system will he replaced.
PROJECTSCHEDULE
Plans and Specs Avail able to Bidders:
1S 02
Bid Opening:
3APR02
Project AwaN:
17APRo2
Construction Start (Phase 1&2):
IMAY02
Conswc0on Complew (Phase 2):
1SAU002
Construction Start (Phase 3):
16AUG02
Construction Complete (Plate. 1&3):
1 ROCT02
Construction Stan (Phase 4):
1MAY03
Construction Complete (Phase 4):
15AUGo3
Note: UID Form 1391 documcnmtlon is used to establish scope
Page s
O2-160
Page e
02 -IW
TECFSJICAL APPENDIX B
STATEpAE TOF WORK
CITY OF BANGOR DESIGN
1. Purpose. This Statement of Work defines the City of Bangors obligation in providing
design for u construction project.
2. Scope of Services. By contract or in-house asking, the City of Bangor will provide the
Amhrea-Engfi ear (A-E) services necessary to develop Plane, specifications, and cast
estimates (referred in m the Project Design Documents) requhed for eonsuvcti m of me
project.
3. Arclsitect-Engineer Services. Architect -Engineer Services shall be designated in the
following manner'
3.1. Title hType "A" Concept Services: Field surveys and investigations required to
obtain date essential For the pmduaion orplans end specifications for construction which
may include, but not be limited to, topographical surveys, soil borings, soils, chemical
and mnchughad surveys and investigations, survey of utility, location and capacities, and
similar fort -finding investigations and technical studies.
3.2. Title n1ypc "B" Architect -Engineer Services: Services as perform code and aitedn
review and in produce construction plans, construction specifications and construction
estimates et the preliminary (35 percent completion), pre -final (95 percent complained
and anal (bidding documents) pluses.
33. Reproduction Services: Services to repfalme construction plans and Vociiicauons
suitable for bidding purposes.
3A. 91 tie Wrype "C" Construction Supervision Service: Services to supirmou and
inspect construction performance and review of construction conbanamf prepared ass -built
drawings. This service will be provided as part of the State Cnnsumtion Appendix,
paragraph 24.1.
4. projecr Schedule. The parties agree m exorcise theirbest efforts to complete the project
design within the period set forth on the Project Schedule contained in this Appendix.
5. Design Responsibilities.
5.1. City of Banger Design.
Federal funds aro not yet available For design and construction of the punier
5.1.1. The City of Bang" will erica and contract for A-E dici services.
02-160
5.1.2. ANG shall not issue directions m the City f Bangols design A -la and shall
communicate with the City of Bangor's design A-E only through, or with the permission
of, an authorized representative of the City of Bangor.
5.1.3. The City of Bangor shall carry out final design of the pmject as defined in this
Appendix. The forth design shall include construction plans and specifications,
construction cost estimates, the consruc0on schedule, and any applicable phasing or
sequencing requirements.
5.2. Title to Design Documents. Tide to Design Doeume is shall be provided in the City
of Bangor I)csign conduct. The City of Bangor shall insure that the design contract
provides an unlimited right to axe of Design D cumene% at no additional cost
5.3. Limitation of liability.
5.3.1 The City of Bangor acknowledges that It for its contractor) is preparing Design
Documents in its tight and not as an agent or contractor of NGB_
5.3.2, No NOB or City of Bangor approval given under this Appendix shall be construed
as a warranty of any kind.
6. Reimbursement of Design Costs.
6.1 Reimbursement of design costs will be included in payments during the course of
construction by adding to the Federal share of these costs to the Fe lcml sham of the
construction Cos" RM deducting from the City of Bangor's contribution to concoction
corns, if any. If there is no City of Bangor nhmn, Fecund! miniburnanent of supportable
design costs shall be by dime[ payment m tic City of Bangor.
7. Am6imut-Enginar Fee limits
7.1. Architect-Engineor fee percentages are determined according to the Typical
Architecmml-Engineering Fees for ANG projects of Architect -Engineer Services for
National Guard Projects.
7.2. As an alternative, the City of Bangor may choose to negotiate a fixed fee Amhucet-
Engimx:rswvizs contract. If the fixed fee option is chosen, in addition many other
llmiration on con ad forth in this MCCA, NOD shall have no obligation As reimburse the
City of Bangor for more than the Fadctal prorate share of.
71.1. Tide Ulype A, Concept, costs in excess of 2% (unless approved in advance by
NOD) of the estimated cost of construction;
7.2.2. Title (iCype B, Design, costs in excess of 6% of the estimated cost of construction
Page Bite
02-160
7.2.3. Bid Document Reproduction in excess of 25 sets (unless approved in advance by
NGB) of bid documents: and,
7.2.4. Title UNWe C, Cmohructhm Supmviaion, costs in excess of 2% of the cauntiod
caer of construction_
TYPICAL JUt=EMIR AI.HNGMGCR ING FECS FOR AIR
Exlirnewl Comnauton Cmt
AreNleet-Hn(iMering Conrad Tutu Amount
Up to$EW,M
IUs
Greater than 52M." B uP w§8n0.W0
9%
Grcaw Man.5800AM1U@uymE2.000.W0
BLL
Greater Man 52UW.W0
7%
9.1 Project Design Finance Plana
9.1. The project li mance plan is the maximum amount for which NOR is obligated to
minburac the City of Bangor for the cost of performance of Mia MCCA. The amount of
any project finance plan line them cost limitation shall not be exCMdcd.
9 2. Unless otherwise provided tar in the project f mance plan, any line item therein may
he clmnged only by amendment of this MCCA. Either patty may propose a change in
finance plan by submitting such proposal in writing to the other party. Use NGR 5-
IIANGI63-101, Appendix E, Cooperative Agreemml Modi ficatinn fimn or Standard
Form 30.
Page 9110
02-160
FKNN992371 Repair Airfield Pavements, BTA
ESTDrIATFD COSI OF CONSTRUCTION: S14,60[1,000
Design finance Plan None. Terms and Conditions:
1. This Design Finance Plan is incorporated Imo this Appendix for the purpose of
establishing the total estimated casts and the amount of NOB Funding necessary, to
produce project Design Documanh, to am forth the estimated amount of the City of
Bangor's share of design Costa, die costs of which ate funded by NGB for the account of
the City of Bangor, and to identify the costs for cost shared. I W%NGB and 100% City
oFBangordcsign.
2. In accordaott with this Appendix, and subject hh any mhcr cost or fund Initiation iiation in
this MCCA, NGB shall reimburse the State for lW%of allowable conn of for dcsi gn of
ANO improvements which include: Punions of the investigative and design services for
the runway, taxiways 'IC and "M", and the north and south bold aprons.
3, NOB shall not bo liable in reimbume the City of Bangor for any other costs of design
except those for cost shared or ANG improvemmis
Estimated
Bid mu
Eadmated
Estirwsed
Activity
ANGShom
City
Share
Other Shoff
fatal
Site
$
24,Wa
$
96,0W
$
0
$ 120,WU
Investigation
Design of
Cast Shared
$
113,000
$
133,W0
$
0
$ 2{6,000
im encs
Design of
ANG
S
33,000
S
35,OW
$
0
$ 68,0110
M rovemcnis
Dcsign of nry
r
of Bangor
$
0
$
0
$
0
$ 0
m veman n
Tough
$
170,000
$
264,aW
$
0
$ 414,000
ESTDrIATFD COSI OF CONSTRUCTION: S14,60[1,000
Design finance Plan None. Terms and Conditions:
1. This Design Finance Plan is incorporated Imo this Appendix for the purpose of
establishing the total estimated casts and the amount of NOB Funding necessary, to
produce project Design Documanh, to am forth the estimated amount of the City of
Bangor's share of design Costa, die costs of which ate funded by NGB for the account of
the City of Bangor, and to identify the costs for cost shared. I W%NGB and 100% City
oFBangordcsign.
2. In accordaott with this Appendix, and subject hh any mhcr cost or fund Initiation iiation in
this MCCA, NGB shall reimburse the State for lW%of allowable conn of for dcsi gn of
ANO improvements which include: Punions of the investigative and design services for
the runway, taxiways 'IC and "M", and the north and south bold aprons.
3, NOB shall not bo liable in reimbume the City of Bangor for any other costs of design
except those for cost shared or ANG improvemmis
Page 10110
02-160
PROJECT DESCRBTION, SCOPE, AND SChUbDULE
The project description for design includes: Repair airEeld pavements through a socks of
concrete reconstruction and overlay, with bitumin0 5 pevemenr. Change the width of the
runway from 300' to NO'. Replace runway and taxiway electrical systems. Reconstruct
taxiwave "r' and W' as well as beth the north and south hold aprons. Project will be
phased over two years.
PROJECT SCOPE
This project includes reconstruction and bimminous overlay of an 11,440' X 200'
concrete runway. The existing runway is 300' wide requiring the airfield lighting to be
relocated The entire runway light system will be replaced. Also included in the mol
scope is reconstruction and bituminous overlay of bods the North and South hold pubs.
Finally, the project will rehab bath mxiway'W and W'. All new pavements wilI be
biturmorms with the exception of a vim pad located in the North hold pad.
PROJECTSCIIEDUI.E
The project design is complete the following is the construction schedule for the project.
Plans and Specs Available to Bidders: 15FEB02
Bid Opening: 3APR02
Project Award: 17APRO2
Convection Stan (Phase 1&2): 1MAY02
Construction Complete (Phase 2): 15AUO02
Construction Stan (Phase 3): 16AUO02
Construction Complete (Phase 1&3): 16OCT02
Carmarthen Stan (Phaw 4): 1MAY03
Construction Complete (Phase 4): 15A0003
Nose: DD Form 1391 documentation is used to establish scope