HomeMy WebLinkAbout2015-11-09 16-009 ORDERCOUNCIL ACTION
Item No. 16-009
Date: November 9, 2015
Item/Subject: ORDER, Authorizing Execution of Agreement for Maine Department of
Transportation Local Project — Griffin Road Mill & Fill, WIN
22516.02
Responsible Department: Engineering
Commentary:
This order would authorize the City Manager to execute a Local Project Agreement with the
Maine Department of Transportation for design and construction of a project on Griffin Road
beginning at the intersection of Union Street and extending northerly approximately 0.46 miles
to Ohio Street. Work will consist of a two inch mill and fill with ADA and drainage improvements.
The Maine Department of Transportation has approved state funds in an amount not to exceed
$460,000.00. Total State share of 50% to equal $230,000.00, and a Municipality share of 50%
to equal $230,000.00. As part of that project, the City would need to enter into a local project
agreement with the Maine Department of Transportation. This item will be discussed at a pre -
council on November 9, 2015.
Manager's Comments:
Associated Information: Council Order, Agreement
Budget Approval:
Legal Approval:
John M. Theriault, PTOE, PE
Department Head
Finance Director
City Solicitor
Introduced for
X Passage
First Reading Page _ of _
Referral
16-009
NOVEMBER 9, 2015
Assigned to Councilor Plourde
CITY OF BANGOR
(TITLE.) Order, Authorizing Execution of Agreement for Maine Department of
Transportation Local Project — Mill & Fill, WIN 22516.02
(TITLE.) ORDER, Authorizing Execution of Agreement for Maine Department of
Transportation Local Project — WIN #22516.02, Griffin Road Mill and Fill Project
ORDERED,
THAT: the City Manager is hereby authorized and directed to execute an agreement with the
Maine Department of Transportation for the following:
An Agreement with the Maine Department of Transportation — Griffin Road Mill and Fill
Project, WIN #22516.02
Copy of the agreement is attached.
IN CITY COUNCIL
NOVEMBER 9, 2015
PASSED
CITY CLE
16-009
NOVEMBER 9, 2015
rnterml use Only
r,�nacs a:
cry:
C Asx#:
STATE OF MAINE DEPARTMENT OF TRANSPORTATION
MUNICIPAL PARTNERSHIP AGREEMENT
WIN 22516.42
REGARDING
GRIFFIN ROAD MILL AND FILL PROJECT, BANGOR
This Cooperative Agreement (AGREEMENT) is entered into by and between the MAINE
DEPARTMENT OF TRANSPORTATION ("MaineDOT"), an agency of state government with its
principal administrative offices located on Child Street, Augusta, Maine, and the CITY OF BANGOR
("Bangor"), a municipality in the State of Maine with offices located at 73 HARLOW STREET,
BANGOR, ME.
WHEREAS, Bangor shall oversee the design and construction of a project on Griffin Road beginning
at the intersection of Union Street and extending northerly approximately 0.46 miles to Ohio Street.
The work will consist of a 2 inch mill and fill with ADA and drainage improvements. Bangor
estimates the total cost of this project to be 5460,000.00.
BANGOR SHALL:
A. Shall procure and oversee a project on Griffin Road for the work outlined above.
B. Perform such work in accordance with a design by an engineer licensed in the State of Maine.
The Licensed Engineer shall provide a certification to the Municipality and to MaineDOT that,
in his/her professional opinion, the Project as designed will provide a smooth ride, not reduce
the safety, mobility or structural quality of the state [state aid] road. All design documents
must be stamped and signed in accordance with this provision by the Professional Engineer.
C. Agree to secure all necessary Federal, State and Local permits necessary to complete the work.
Bangor also agrees to secure any needed property rights in accordance with all applicable State
and Federal Laws.
D. Agree that any exceptions to State Design Standards shall be documented as part of this
process. This documentation shall compare the new design to the existing conditions for each
of the exceptions to current design standards. Any such exceptions shall be displayed on the
cover sheet for the Project plans with the signature and PE stamp of the engineer responsible
for the design of the Project.
E. Be responsible, within the Project limits, for the following:
Rev. 7/30/10
16=009
NOVEMBER 9, 2015
a. Ensuring that the safety of the corridor and the life of the resulting structural and design
elements are equal to or better than existing conditions and design;
b. Ensuring that the structures, roadways and/or design features affected by the Project
work shall, at a minimum, be of equal dimensions to the existing features or structures
and shall be of improved quality in terms of materials and utility;
c. Ensuring that the Project does not introduce any unanticipated safety hazards to the
traveling public;
d. Ensuring that the Project retains the same level of mobility or improves mobility of
travel within the corridor; and,
e. Ensuring that the Project does not in any manner decrease the life expectancy of this
component of Maine's transportation system.
f Ensure the project meets the most recent Americans with Disabilities Act of 1990
(ADA) design requirements.
F. Provide certification through their Engineer to MaineDOT that the project is complete and was
constructed as designed.
G. Commence construction within twelve (12) months and shall be certified complete within
twenty four (24) months of execution of this agreement. Bangor may forfeit the unpaid balance
of this grant if these deadlines are not met or they can not demonstrate earnest and good faith
efforts to meet them.
MAINEDOT SHALL:
A. Provide a maximum of $230,000.00 in State funds supporting the project work stated above
in initiative monies. Reimbursement will be made by the Department at a minimum of 1/3 project
completion upon receipt of supporting cost documentation from the Municipality. Payments will be
made per Appendix A, attached. The Department's Region Engineer shall review the costs and
certify their eligibility prior to reimbursement to the Municipality. Payment by MaineDOT
Municipal Partnership Initiative funds shall not exceed 50% of the actual costs incurred and paid
by the Municipality or $230,000.00.
The City of Bangor and MaineDOT agree to function within all applicable laws, statutes, regulations,
and AGREEMENT provisions; avoid hindering each other's performance; fulfill all obligations
diligently; and cooperate in achievement of the intent of this AGREEMENT.
Rev. 7/30/10
16-009
NOVEMBER 9, 2015
IN WITNESS WHEREOF, the parties hereto have executed this AGREEMENT in duplicate
effective on the day and date last signed,
CITY OF BANGOR
Dated:
Catherine Conlow
City Manager
STATE OF MAINE
DEPARTMENT OF TRANSPORTATION
Dated:
David Bernhardt, PE
Commissioner
Rev. 7!30110
16-009
NOVEMBER 9, 2015
APPENDIX A
PROJECT SCOPE AND COST SHARING
MAINE DEPARTMENT OF TRANSPORTATION
Municipal Partnership Initiative Project
MUNICIPALITY OF Bangor
PROPOSED IMPROVEMENTS TO: Griffin Road
STATE PROJECT IDENTIFICATION NUMBER (WIN) 22516.02
Pro iect Scope:
Fundina Outline: The Total Project Estimated Cost is and the Panics agree to share costs through all stages of the Project under the
terms outlined below.
Project Casts
'00 50 230,000.00 46(,Q00.00
PROJECT ARES
2306100.00 230,000.00 460,000.00
Total Cost of Additional
Work above agreement
estimate
TOTAL ESTIMATED
MUNICIPAL
230,000.00
REIMBURSEMENT
REIMBURSEMENT SCHEDULE:
YES ..= NO
16-009
NOVEMBER 9, 2015
Design exceptions where required for this project. Please see attached approval from MaineDOT Chief Engineer outlining design exceptions.