HomeMy WebLinkAbout1970-06-08 200-X ORDER200-x
Introduced by Councilor Nealley, J1ne 8, 1970
CITY OF BANGOR
(TITLE.) @r[brerr...... d ceptmg Report of city engineer Storm Sewer Dunning
Boulevard -- And Approorlatinq Funds
By Mie City Cmnidl of the MV urBangor:
ORDERED,
THAT the attached report of the City Engineer relative
to the construction of a storm sewer on tanning Boulevard be
and hereby is accepted, and, be it further
ORDERED, that necessary fonds be appropriated and that con-
struction begin as soon as possible.
IVES
1910 .NN
CITY CLEfin's OV FICF.
IN CITY COUNCIL
June B, 1970
PASSED
z00 -x
ORDER
Title,
..REB%F. Sity, angineu - storm swez
..wooing, Biya.............. I.........
Introduced and filed by
.:........... .....
Councilman
CITY OF BANGOR, MAINE
Engineering Department
June 4, 1970
TO: The Municipal Officers
Pursuant to Council Order 134-X, passed April 13, 1970,
directing the City Engineer to make the necessary surveys and
prepare plans and cost estimates for the installation of a
storm sewer on Dunning Boulevard, the following report is sub-
mitted:
The installation would consist of 500 feet of 10 -inch
asphalt coated corrugated metal pipe and two manholes, said
storm sewer to extend westerly on Dunning Boulevard from aex-
isting storm sewer on Union Street. Two existing catch basins
would be connected to the upper end of said sewer. This would
eliminate all surface water from the existing Sewer On Dunning
Boulevard and Westland Street, which connects
ects into the Ohio
Street sewer, previously separated under another project.
The total estimated cost of this project is $5500. It is
recommended that the sewer be installed. A plan showing the
proposed installation is attached.
Respectfully submitted,
JO£ awaw e
City Engineer
JTF:L
Attachment