HomeMy WebLinkAbout1979-12-26 53 AH ORDER53 As
Introduced by Councilor Soucy, December 26, 1979
T1- CITY OF BANGOR
zz
(TITLE.) 41iriter...... ... Authorizing, Payment of Architect ral Fees and
Costs- Ba ........... .... _.............. ........... _.1.
By the Gley Coundl of the City of Beeper.
ORDERED,
THAT the Finance_ Director is hereby authorized and directed
to pgy out
of "Reserve. for Future Construction - General" the
sum of $23,448.56 for architectural services and related costs
incurred by the City in conjunction with the design and the
construction of the Bangor Civic Center.
Statement of Fact: Architectural s ices for the design and
'construction of the Bangor Civic Center were performed by
Eaton W. Tarbell & Associates, Inc., of Bangor. During
the course of construction many of the charges submitted
by the architect were disputed by the City staff. Pursuan
to the contract between the City and the architect, eight
of the disputed claimswere considered by anarbitrator
appointed by the American Arbitration Association. Of the
eight original claims totaling $44,231.50, six claims in
the amount of $21,227.50 were dismissed as un ustified.
The remaining balance of two claims totaling $23,004 were
awarded by the arbitrator to the architect. In addition,.
there remains a total of $444.56 to be paid by the City as
its share of the costs of the arbitration proceedings.
53 AH
IN CITY COUNCIL 0 R 0 E R -
December 26,, 1979
Title, '79 DEC 20 W9 49
t� T^✓� Authorizing eaymevt of cxxs cLMV ..ArchiYectv[al RECEIV LU
...................... CI Y OF t
CITY CLERK
Fees and Cont..... - Bango...6.. Civic Center.4.....
Introduced pnd d by