HomeMy WebLinkAbout2016-08-08 16-296 ORDERCOUNCIL ACTION
Item No. 16-296
Date: AUGUST 8, 2016
Item/Subject: ORDER, Authorizing Execution of Agreement for Maine Department of
Transportation Project — Outer Hammond Street Pavement
Preservation Project, WIN 21926.04
Responsible Department: Engineering
Commentary:
This order would authorize the City Manager to execute a Municipal Partnership Agreement with
the Maine Department of Transportation for a 1 1/2 inch overlay (with shim), pavement
preservation project on Outer Hammond Street (Route 2) beginning approximately 0.05 miles
northerly of Doane Street and extending northerly 0.99 miles.
The Maine Department of Transportation has approved funds in an amount not to exceed
$548,612.00. The total State/Federal share of 50% is equal to $274,306.00, and the
Municipality share of 50% is equal to $274,306.00. As a condition of this funding, the City is
required to enter into a Municipal Partnership Agreement with the Maine Department of
Transportation. This item was reviewed and recommended for approval at the Infrastructure
Committee meeting on May 24, 2016.
Manager's Comments:
Associated Information: Council Order, Agreement
Budget Approval:
Legal Approval:
Introduced for
X Passage
First Reading
Referral
John M. Theriault, City Engineer
Department Head
F1
r1City Managea
Finance Director
Ci Solicitor
Page _ of _
Assigned to Councilor Nealley
CITY OF BANGOR
16-296
AUGUST 8, 2016
(TITLE.) Order, Authorizing Execution of Agreement for Maine Department of
Transportation Project — Outer Hammond Street Pavement
Preservation Project, WIN 21926.04
(TITLE.) ORDER, Authorizing Execution of Agreement for Maine Department of
Transportation Project — WIN #21926.04, Outer Hammond Street Pavement Preservation
Project.
ORDERED,
THAT: the City Manager is hereby authorized and directed to execute an agreement with the
Maine Department of Transportation for the following:
An Agreement with the Maine Department of Transportation — Outer Hammond Street
Pavement Preservation Project, WIN #21926.04
Copy of the agreement is attached.
IN CITY COUNCIL
AUGUST 8, 2016
PASSED
�p� A-)
CITY CLERK
16-296
AUGUST 8, 2016
r _ interna Use Only
rEDocs #:
Cr#:
esiv#:
i
STATE OF MAINE DEPARTMENT OF TRANSPORTATION
MUNICIPAL PARTNERSHIP AGREEMENT
WIN: 21926.04 Bangor, Outer Hammond Street
REGARDING a Pavement Preservation Project
This Cooperative Agreement (AGREEMENT) is entered into by and between the MAINE
DEPARTMENT OF TRANSPORTATION C'MaineDOr), an agency of state goveni meat with its
principal administrative offices located on Child Street, Augusta, Maine, and the City of Bangor
("Bangor"), a municipality in the State of Maine with offices located at 73 Harlow Street, Bangor, ME.
WHEREAS, Outer Hammond Street (Route 2) is in need of pavement preservation to prolong the life
of the highway infrastructure.
WHEREAS, Bangor shall develop and oversee a pavement preservation project on Outer Hammond
Street beginning approximately 0.05 miles northerly of Doane Street and extending northerly 0.99
miles. The City estimates the cost to do a 1 1/2 inch overlay (with shim) on Outer Hammond Street to
be $548,612.00. MaineDOT and the City of Bangor have agreed to cost share in the development and
construction of the project.
THE CITY OF BANGOR SHALL:
A. Procure all contracts for and oversee Project on Muter Hammond Street for the work outlined
above.
B. Cause such Work in accordance with a design by an engineer licensed in the State of Maine.
The Licensed Engineer shall provide a certification to the Municipality and to MaineDOT that,
in his/her professional opinion, the Project as designed will provide a smooth ride, not reduce
the safety, mobility, or structural quality of the state [state aid] road. All design documents
must be stamped and signed in accordance with this provision by the Professional Engineer.
C. Agrees to secure all necessary Federal, State and Local permits necessary to complete the
Work. Bangor also agrees to secure any needed property rights in accordance with all
applicable State and Federal Law.
D. Agrees that any exceptions to State Design Standards shall be documented as part of this
process. This documentation shall compare the new design to the existing conditions for each
of the exceptions to current design standards. Any such exceptions shall be displayed on the
cover sheet for the Project plans with the signature and PE stamp of the engineer responsible
for the design of the Project.
E. Be responsible, within the Project limits, for the following:
a. Ensuring that the safety of the corridor and the life of the resulting structural and design
elements are equal to or better than existing conditions and design;
Rev. 7130/10
16-296
AUGUST 8, 2016
b. Ensuring that the structures, roadways and/or design features affected by the Project
work shall, at a minimum, be of equal dimensions to the existing features or structures
and shall be of improved quality in terms of materials and utility;
c. Ensuring that the Project does not introduce any unanticipated safety hazards to the
traveling public;
d. Ensuring that the Project retains the same level of mobility or improves mobility of
travel within the corridor;
e. Ensuring that the Project does not in any manner decrease the life expectancy of this
component of Maine's transportation system; and,
f Ensuring the project meets the most recent Americans with Disabilities Act of 1990
(ADA) design requirements.
F. Provide certification through their Engineer to MaineDOT that the Project is complete and was
constructed as designed.
G. Ensure that construction shall commence within twelve (18) months and shall be certified
complete within twenty (36) months of execution of this agreement. Bangor may forfeit the
unpaid balance of this grant if these deadlines are not met or they cannot demonstrate earnest
and good faith efforts to meet them.
H. Be responsible for or cause its contractors to be responsible for all damage to public or private
property of any kind resulting from any act, omission, neglect or misconduct of Bangor or its
contractors, including damage to vehicles passing through the Project limits.
I. Bear all risk of loss relating to the Project and the Work regardless of cause.
MAINEDOT SHALL:
Provide a maximum of $274,306.00 in State funds supporting the project Work stated
above. Reimbursement will be made by the Department at a minimum of 1/3 project completion upon
receipt of supporting cost documentation from the Municipality. Payments will be made per Appendix
A, attached. The Department's Region Engineer shall review the costs and certify their eligibility prior
to reimbursement of Municipal Partnership Initiative Funds. Payment by MaineDOT Municipal
Partnership Initiative funds shall not exceed $274,306.00 or 501% of the actual costs incurred and paid
by the Municipality.
The City of Bangor and MaineDOT agree to function within all applicable laws, statutes, regulations,
and AGREEMENT provisions; avoid hindering each other's performance; fulfill all obligations
diligently-, and cooperate in achievement of the intent of this AGREEMENT.
[SIGNATURES ON FOLLOWING PAGE]
Rtv. 7/30110
16-296
AUGUST 8, 2016
IN WITNESS WHEREOF, the parries hereto have executed this AGREEMENT in duplicate
effective on the day and date last signed.
CITY OF BANGOR.
Dated: By:
Catherine Conlow, City Manager
STATE OF MAINE
DEPARTMENT OF TRANSPORTATION
Dated • By:
David Bernhardt, PE
Commissioner
Rtv. 7/30/10
16-296
AUGUST 8, 2016
APPENDIX A
PROJECT SCOPE AND COST SHARING
MAINE DEPARTMENT OF TRANSPORTATION
Municipal Partnership Initiative Project
MUNICIPALITY OF BANGOR
PROPOSED IMPROVEMENTS TO: Outer Hammond Street
STATE PROJECT IDENTIFICATION NUMBER (WIN) 21926.04
Project Scone: 1 1/2 inch overlay (with shfin)
Fun -dint Ondine The Total Project Estimated Cost is Jl4MM and the Parties agree to share costs through all stages of the Project under the
terms outlined Wow.
Work Element
Municipal Share
State Share
Total Cost
Project Costs
274,306.00
50 274.306.00
548,612.00
PROJECT SHARES
Total Cost of Additional
Work above agreement
estimate
TOTAL ESTIMATED
MUNICIPAL
REIMBURSEMENT
16-296
AUGUST 8, 2016
REIMBURSEMENT SCHEDULE:
DESIGN EXCEPTIONS REQUIRED a YES NO
Design exceptions where required for this project. Please see attached approval from MaineDOT Chief Engineer outlining design exceptions.