Authorizing Execution of a Contract Change Order with Gordon Contracting Inc in the Amount of $550,000 to
Complete Phase II Replacment of Climber Screens at the Wastewater Treatment Facility
This Order will authorize the execution of a change order to a contract with Gordon Contracting Inc
in the amount of $550,00 to replace the climber screens at the wastewater treatment facility.
On December 18, 2019, the City received three bids for a two phase project to replace the climber
screens at the Kenduskeag pump station and the wastewater treatment facility. On January 13,
2020, Council funded and awarded phase I (Kenduskeag pump station). The bid included Phase II
with the understanding that it would be awarded when the funding was available. Phase II of the
work was funded in the 2021 budget so effective on July 1, funding was available.
This was approved and recommended at a Finance Committee of January 6, 2020. Phase I was
awarded on January 13, 2020.
Finance Committee
08/03/2020
Recommend for passage
50
Consent
08/10/202020-249
CITY OF BANGOR ORDER
08/10/2020
20-249
Schaefer
Authorizing Execution of a Contract Change Order with Gordon Contracting Inc in the Amount of $550,000 to
Complete Phase II Replacment of Climber Screens at the Wastewater Treatment Facility
Whereas, on December 18, 2019, the City received three bids to complete Phase I and IIof replacement of
climber screens at Kenduskeag Pump Station (KPS) and the Waste Water Treatment Plant; and
Whereas, the bids received ranged from $1,382,000 - $1,731,857.
Whereas, Phase I of the project, in the amount of $832,000, was awarded on January 13, 2020; and
Whereas, Phase II of the project, if approved, is approximately $550,000 for replacement of climber screens
at the waste water treatment facility.
Be it Ordered by the City Council of the City of Bangor that
The Finance Director is hereby authorized to execute a contract change with Gordon Contracting Inc. in the
amount of $550,000 to complete Phase II replacement of the climber screens at the wastewater treatment
facility.
IN CITY COUNCIL
AUGUST 10,2020
CO 20-249
Motion made and seconded for Passage of Consent Agenda
Vote: 9—0
Councilors Voting Yes: Fournier,Hawes,Nichols,Okafor, Schaefer, Sprague, Supica, Tremble,Davitt
Councilors Voting No: None
Passed