HomeMy WebLinkAbout2020-04-13 20-120 Order
04/13/202020-120
04/13/2020
20-120
Engineering
Order
N/A
Title, Order
Authorizing City Manager to Execute a Municipal Partnership Agreement with Maine Department of
Transportation - WIN 024317.02, Stillwater Avenue
The Order would authorized the City Manager to execute a Municipal Partnership Agreement with
Maine Department of Transportation for a portion of Stillwater Avenue.
The scope of the project consists of a mill and fill of 1 1/2 inch mill and overlay of existing pavement
with a 1/2 shim, and replacement of bituminous curb with slip form concrete curb on Stillwater
Avenue, beginning at the southerly intersection of the Bangor Mall and extending northerly 0.89
miles to Hogan Road.
The total project estimate is $860,000.00, with the State Share of $430,000.00 or 50%, and City
Share $430,000.00 or 50%.
This project has been approved to commence construction for calendar year 2021.
Infrastructure Committee
04/07/2020
Recommend for passage
50
Staff recommends approval of the attached MaineDOT Municipal Partnership Agreement.
Consent
04/13/202020-120
CITY OF BANGOR ORDER
04/13/2020
20-120
Nichols
Authorizing City Manager to Execute a Municipal Partnership Agreement with Maine Department of
Transportation - WIN 024317.02, Stillwater Avenue
Be it Ordered by the City Council of the City of Bangor that,
The City Manager is hereby authorized and directed to execute a Maine Department of Transportation
Municipal Partnership Agreement for Stillwater Avenue, WIN #024317.02.
20-120
APRIL 13, 2020
Internal Use Only
TEDOCS #: _______________________________
CTM#:_________________________________________________
CSN#: ________________________________
STATE OF MAINE DEPARTMENT OF TRANSPORTATION
MUNICIPAL PARTNERSHIP AGREEMENT
WIN 024317.02
REGARDING
BANGOR,STILLWATER AVENUE
This Cooperative Agreement (AGREEMENT) is entered into by and between the MAINE
DEPARTMENT OF TRANSPORTATION(“MaineDOT”),an agency of state government with its
principal administrative offices located on Child Street, Augusta, Maine, and the CITY OFBANGOR
(“MUNICIPALITY”),a municipality in the State of Maine with offices located at 73 Harlow Street,
BANGOR, ME.
WHEREAS,
BANGORshall perform amill and fillprojectconsisting of a1 ½ inchoverlay of existing pavement
with a ½ inch shim,and replacement of bituminous curb with slip form concrete curb on Stillwater
Avenue, beginning at the southerly intersection to the Bangor Malland extending northerly 0.89miles
(RLM 1.48 to RLM 2.37) to Hogan Road(the “Project”). BANGORestimates this project at
$860,000.00.
BANGORSHALL:
A.Procureall contractsfor and overseethe Project on STILLWATER AVENUEfor the Work
outlined above.
B.Cause such Work to be performed in accordance with a design by anengineer licensed in the
State of Maine. The Licensed Engineer shall provide a certification to the Municipality and to
MaineDOT that, in his/her professional opinion, the Project as designed will provide a smooth
ride, not reduce the safety, mobility or structural quality of the state \[state aid\] road. All design
documents must be stamped and signed in accordance with this provision by the Professional
Engineer.
C.Agreeto secure all necessary Federal, State and Local permits necessary to complete the work.
BANGOR also agrees to secure any needed property rights in accordance with all applicable
State and Federal Law.
D.Agree that any exceptions to State Design Standards shall be documented as part of this
process. This documentation shall compare the new design to the existing conditions for each
of the exceptions to current design standards. Any such exceptions shall be displayed on the
cover sheet for the Project plans with the signature and PE stamp of the engineer responsible
for the design of the Project.
E.Be responsible, within the Project limits, for the following:
a.Ensuring that the safety of the corridor and the life of the resulting structural and design
elements are equal to or better than existing conditions and design;
Rev. 11/14/2018
20-120
APRIL 13, 2020
b.Ensuring that the structures, roadways and/or design features affected by the Project
work shall, at a minimum, be of improved quality in terms of materials and utility;
c.Ensuring that the Project does not introduce safety hazards;
d.Ensuring that the Project retains the same level of mobility or improves mobility of
travel within the corridor, unless approved traffic calming measures are proposed;
e.Ensuring that the Project does not decrease the life expectancy of this component of
Maine’s transportation system; and,
f.Ensuring that the Project meetsthe current standards of Americans with Disabilities Act
of 1990 (ADA) design requirements.
F.Provide certification through their Engineer to MaineDOT that the Project is complete and was
constructed as designed.
G.Ensure that construction shall commence within EIGHTEEN (18) months and shall be certified
complete within THIRTY-SIX (36) months of execution of this agreement.BANGOR may
forfeit the unpaid balance of this grant if these deadlines are not met or they can not
demonstrate earnest and good faith efforts to meet them.
H.Be responsible for or cause its contractors to be responsible for all damage to public or private
property of any kind resulting from any act, omission, neglect or misconduct of BANGORor
its contractors, including damage to vehicles passing through the Project limits.
I.Bear all risk of loss relating to the Project and the Work regardless of cause.
MAINEDOT SHALL:
A.Provide a maximum $430,000.00 in State funds supporting the Work stated above.
Reimbursement will be made by the Department at a minimum of 1/3 project completion upon
receipt of supporting cost documentation from the Municipality. Payments will be made per
Appendix A attached. The Department’s Region Engineer shall review the costs and certify
their eligibility prior to reimbursement of Municipal Partnership Initiative Funds. Payment by
MaineDOT Municipal Partnership Initiative funds shall not exceed $430,000.00or 50% of the
actual costs incurred and paid by the Municipality.
B.This project has been approved for Calendar Year 2021.If the Municipality commences
construction of the project as outlined above prior to January 1, 2021, the Municipality assumes
the risk and responsibility for costs incurred, in the event that funding levels fall below
MaineDOT projections. If this occurs, the Municipality will not receive reimbursement from
MaineDOT.
The CITY OFBANGOR and MaineDOTagree to function within all applicable laws, statutes,
regulations, and AGREEMENT provisions; avoid hindering each other’s performance; fulfill all
obligations diligently; and cooperate in achievement of the intent of this AGREEMENT.
Rev. 11/14/2018
20-120
APRIL 13, 2020
IN WITNESS,WHEREOF, the partieshereto have executed this AGREEMENT effective on the day
and date last signed.
CITY OFBANGOR
Dated: _________________ By: __________________________________
Catherine M. Conlow
City Manager
STATE OF MAINE
DEPARTMENT OF TRANSPORTATION
Dated: _________________ By: __________________________________
Bruce A. Van Note
Commissioner
Rev. 11/14/2018
20-120
APRIL 13, 2020
APPENDIX A
PROJECT SCOPE AND COST SHARING
MAINE DEPARTMENT OF TRANSPORTATION
Municipal Partnership Initiative Project
MUNICIPALITYOF BANGOR
PROPOSED IMPROVEMENTS TO:STILLWATER AVENUE
STATE PROJECT IDENTIFICATION NUMBER (WIN) 024317.02
FUNDED CONSTRUCTION YEAR2021
Project Scope: 1 ½ inch Overlay
FundingOutline: The Total Project Estimated Cost is $860,000.00, and the Parties agree to share costs through all stages of the Project under the
terms outlined below.
Municipal ShareState ShareTotal Cost
Work Element
%$%$$
50
430,00050430,000860,000
Project Costs
PROJECT SHARES
100%
Total Cost of Additional
Work above agreement
estimate
TOTAL ESTIMATED
$430,000.00
MUNICIPAL
REIMBURSEMENT
20-120
APRIL 13, 2020
REIMBURSEMENT SCHEDULE:
Upon 1/3 project completion, the municipality may begin invoicing the Department. Preferred invoicing interval is 1/3, 2/3, final, the Department
will accept monthly invoices after 1/3 project completion with a maximum invoice submittal not to exceed 5 invoices.
DESIGN EXCEPTIONSREQUIRED:__YES _X__ NO
Design exceptions were required for this project. Please see attached approval from MaineDOT Chief Engineer outlining design exceptions.
IN CITY COUNCIL
APRIL 13,2020
CO 20-120
MOTION MADE AND SECONDED FOR PASSAGE
VOTE: 8-0
COUNCILORS VOTING YES: FOURNIER,HAWES,NICHOLS,OKAFOR, SCHAEFER, SPRAGUE, SUPICA,
TREMBLE
COUNCILORS VOTING NO: NONE
PASSED
CItV CLE