Authorizing City Engineer to submit a grant application for funding through the Maine DEP Stream Crossing
Upgrade Grant program to replace an existing culvert on Grandview Avenue
This Order will authorize the City Engineer to submit a grant application through the Maine DEP’s
Stream Crossing Upgrade Grant Program to remove and replace the crossing of Arctic Brook on
Grandview Avenue, which is currently undersized for the flow volumes.
The grants were made available by a citizen approved bond and the maximum award per project is
$95,000. Bangor is requesting $95,000 dollars to partially fund an estimated project cost of
$156,568.51. The City’s contribution of $61,568.51 to the cost of the project will come from the
Stormwater Utility budget in FY2021. If the grant is awarded to the City, construction of the project
will take place during the summer of 2020 between July 15th and October 1st in accordance with
environmental permitting.
Infrastructure Committee
11/04/2019
Recommend for passage
50
Consent
11/25/201920-014
CITY OF BANGOR ORDER
11/25/2019
20-014
Schaefer
Authorizing City Engineer to submit a grant application for funding through the Maine DEP Stream Crossing
Upgrade Grant program to replace an existing culvert on Grandview Avenue
Be it Ordered by the City Council of the City of Bangor that,
The City Engineer is hereby authorized and directed to submit a grant application through the Maine DEP’s
Stream Crossing Upgrade Grant Program for funding in the amount of $95,000 to remove and replace an
existing culvert that carries Arctic Brook beneath Grandview Avenue.
IN CITY COUNCIL
NOVEMBER 25,2019
CO 20-014
PASSED
'k-,--)(�j /c/