HomeMy WebLinkAbout1986-08-11 86-239 ORDERIntroduced by Councilor McCarthy May 28, 1986
CITY OF BANGOR
(TITLE) Vrbfft Accepting City Engineer's Report — Final Cost of Russon
Avenue Sewer Extension
By the City Couwti ofdw City ofBaw .-
ORDERED,
TUT the attached report of the City Engineer showing the
actual costs of the extension of the sanitary sewer om Russon
Avenue to serve the Morningside apartment project be and hereby
is accepted; end be it further
ORDERED,
TEAT the balance of the Developer's deposit for his share
I
f the work be refunded.
In City Council May 26.1966 66-239
Haas ORDER
c;}- ler - Title,
.'..M PGf+ l Gita.. RxYUwac'a+4 ...
final cost o& Yueson AVenUe sewer Evteneion
Introdu ed and filed by
...
w
`.�.�......
N
N
CITY OF BANGOR, MAINE
Engineering Department
May 13, 1986
To the Municipal Officers:
Reference is made to City Council Order No. 84-346 passed
September 24, 1984 which authorized the extension of the sanitary
sewer in a northeasterly direction on Husson Avenue, in response
to a petition from property Investments, Inc., to serve the
Morningside apartment project. All work has been completed,
consisting of theinstallationof 422 feet of 8 inch sewer and
two manholes.
The actual cost of the sewer installation was $7,610.00,
which compared favorably with the Engineer's Estimate of
$10,000.00. In accordance with the original agreement, fifty
percent of the Cost was to be assessed against property Invest-
ments, Inc., with the remaining fifty percent to be paid by the
City. On that basis, the Developer's share of the actual costs
would be $3 805.00; however, since the Developer made an initial
deposit of 45,000.00, a refund in the amount of $1,195.00 is due.
Accordingly, it is recommended that the refund in the amount of
$11195.00 be made to Property Investments, Inc.
Plans showing the actual sewer installation are on file in
the office of the City Engineer.
Respectfully submitted,
Jed
City Engineer