HomeMy WebLinkAbout2018-08-13 18-311 Order
08/13/201818-311
08/13/2018
18-311
Engineering
Order
N/A
Title, Order
Authorizing Execution of Contract with Burns and McDonnell for Remediation of Secondary Active Zone within
the Penobscot River
This Order would authorize Burns & McDonnell to monitor performance of the sediment cap over the
Secondary Active Zone (SAZ), and prepare and submit an Explanation of Significant Differences
Report for the Inactive Zone (IZ).
The City has been working with representatives of Burns & McDonnell for approximately 18 years to
develop methods to mitigate the coal tar contamination within the Penobscot River. This work is
required a part of the City of Bangor Consent Decree with the State of Maine Department of
Environmental Protection.
Infrastructure Committee
08/06/2018
Recommend for passage
50
Burns & McDonnell Agreement
Consent
08/13/201818-311
CITY OF BANGOR ORDER
08/13/2018
18-311
Nichols
Authorizing Execution of Contract with Burns and McDonnell for Remediation of Secondary Active Zone within
the Penobscot River
WHEREAS, On June 5, 2007 a Consent Decree was entered in the case of City of Bangor v. Citizens
Communications Company providing for remediation of the coal tar in the Penobscot River; and
WHEREAS, statutory and regulatory requirements for amendment to the Consent Decree required that there
be additional studies of the remaining contamination area;
WHEREAS, On September 13, 2017 work was performed for the remediation of the shallow portion of the
Secondary Active Zone (SAZ) to construct a Sediment Cap;
WHEREAS, additional studies are required for post monitoring of the new sediment cap in the Secondary
Active Zone (SAZ); and
WHEREAS, Submission of an Explanation of Significant Difference Report be submitted to the Department of
Environmental Protection for the Inactive Zone (IZ) for future remediation.
Be it Ordered by the City Council of the City of Bangor that,
The City Manager is hereby authorized to execute a contract with Burns & McDonnell for SAZ Post
Construction Monitoring and Preparation and Submission of an Explanation of Significant Difference Report for
the Inactive Zone to DEP.
18-311 08/13/2018
July 24, 2018
Mr. John Theriault
City Engineer
City of Bangor
73 Harlow Street, Bangor, ME 04401
Re: Engineering Proposal
Bangor Landing Sediment
Dear Mr. Theriault:
Burns & McDonnell Engineering Company, Inc. (Burns & McDonnell) is pleased to provide
the City of Bangor (the City) with this agreement for environmental services to be provided on
the referenced project as follows:
PROJECT
Burns & McDonnell and the City agree that Burns & McDonnell will provide professional
services described herein in accordance with and subject to the terms and conditions set forth in
the Master Services Agreement between Burns & McDonnell and the City, dated March 1,
2012.
Bangor Landing Sediment Remediation Studies — Work
Authorization
SAZ Post -Construction Monitoring and Preparation of an ESD for the
Inactive Zone
Objective:
0 To monitor performance of the sediment caps over the PAZ and shallow SAZ and
prepare an Explanation of Significant Differences Report for the Inactive Zone
Scope of Services:
Task 1— Post -Construction Monitoring
0 Perform post -construction monitoring for PAZ and SAZ, (2 monitoring events, each
three days long) for the sediment caps in Dunnett's Cove, and
0 Prepare a monitoring report for submittal to the DEP.
Estimated Cost:
SOf South)Pasa Baad • Madison, W153719
Tek 6084304961 • www.harnsmrd.ram
18-311 08/13/2018
N
Mr. John Theriault
July 24, 2018
Page 2
• Labor and Expenses
Assumptions:
$ 60,000
• Ebullition monitoring will require three days in the field for five staff (two Burns &
McDonnell, three SW Cole) during two mobilizations (one in August, one in September
or October).
• Field work will be performed in fair weather.
• The monitoring report will be approved without substantial modifications by the
MEDEP.
Task 2 - Hydrographic Survey
• Perform a hydrographic survey to document the post -construction conditions for the
SAZ sediment cap for submittal to the USACE.
• Submit the map to the USACOE and MEDEP.
Estimated Cost:
Assumptions:
$ 22,000
• Field work will be performed in fair weather.
• Results of the survey will be submitted to the USACOE in a brief letter report.
Task 3 - Preparation of an ESD Report for the IZ
• Prepare an ESD Report for the IZ based on existing information.
Estimated Cost:
• Labor and Expenses
Assumptions:
$ 40,000
• The ESD report will require two drafts before being accepted by the MEDEP. It is
estimated that the ESD report will require about 120 hours of associate scientist time, 60
hours of assistant scientist time, and 20 hours of drafting.
18-311 08/13/2018
N
Mr. John Theriault
July 24, 2018
Page 3
Task 5 — Regulatory Negotiation
Assist the City with negotiation of the ESD with the MEDEP
Estimated Cost:
Labor and Expenses
Assumptions:
$ 25,000
• Regulatory negotiation will require an estimated 80 hours of associate scientist time, 80
hours of assistant scientist time, and 20 hours of drafting.
• Regulatory negotiation will require two trips to Maine to meet with the City and the
MEDEP.
Task 6 — Project Management
Perform project management functions such as financial management and quality
control.
Estimated Cost:
• Labor and Expenses $ 12,000
Assumptions:
• Project management will require about 8% of labor hours
Estimated Cost:
COMPENSATION
A. Amount of Payment
For the Scope of Services described herein, the City shall pay Burns & McDonnell on a time -
and -materials basis. Burns & McDonnell estimates that our fee for these services will be
$159,000.
B. Invoices
Monthly invoices will be submitted by Burns & McDonnell to the City. Invoices will be based
on Burns & McDonnell's time and materials expenditures for the preceding month.
Please provide your written authorization for these services, which can be accomplished by
signing and returning one copy of this agreement (facsimile or email is acceptable) for our files.
18-311 08/13/2018
N
Mr. John Theriault
July 24, 2018
Page 4
Burns & McDonnell appreciates this opportunity to serve the City. If you have questions or
comments concerning this proposal, please call me at (608) 630-4961.
Sincerely,
BURNS & MCDONNELL ENGINEERING COMPANY, INC.
Eugene L. McLinn
Sediment Team Leader
elm
ACCEPTED BY: City of Bangor
Change Order Bangor Landing Sediment............................................................. $159,000
LM
Title
Date
IN CITY COUNCIL
AUGUST 13, 2018
CO 18-311
PASSED
OEr_aeia.4.„).