HomeMy WebLinkAbout1989-05-08 89-201 ORDERDate 5/8/89^"'v' Item No.g9=201
Item/Subject: Accepting City Engineer's Report - final Cost of Sanitary Sewer
Extension on Stillwater Avenue and Hagan Brad
Responsible Department: Engineering
Commentary:
This project covers the extension of the sanitary sever last summer
on Stillwater Avenue to Hogan Road, and easterly on Hogan Roadto
serve the new motel constructed by Miramar Properties. Inc., and the
new automobile lubeservice business constructed by Richard Bean.
ircadoerttaed-Lm—'
x7 Z
Manager's Comments:.�l way ,o;�p ��sep'nonen Hard
ISD#a.l)..r9e-..twaQ.Q..wxaxrP.i9.�"n.-PP""^'."AnuW r't,Imv
aU kxa� 1� AXP
Chy Memgn
AasociatM Information :0 „.440*
Budget Approval: `f"
F11111 01,1
Legal Approval
<i�y Sol
Introduced For
Passage
❑ First Reading Paye _ of
®Referral
89-201
Assigned toCounegot England, May 8, 1989
CITY OF BANGOR
(TITLE.) VIYT31BTa ,Accepting city Engin a export - Final Coat of sanitary. sewer
Exte i on straw t Avenue ana_Hogau Rona
BY the City CouamW of CRY mfBawmw,.
ORDERED,
TEAT the attached report of the city Engineer showing the final cants
and recommended assessments for the extension of the sanitary sewer in a
northerly direction efor eatdistance of 367 feet on Stillwater Avenue, and
easterly on Hagan Road for a distance of 200 feet be and hereby is accepted;
and be it further
ORDERED,
THAT said sewer assessments be assessed as Deco®lhded.@n said report.
�m
ORDER
Title,
9 aty ihy�s tQntt YLal Oat E
........................ 4.............
�itazy &v.3 FUaew�m Stllh�ahxA aril
......................................
" w ,
.....................
Oounellman
89-201
CITY OF BANGOR, MAINE
Engineering Department
April 3, 1989
To the Municipal Officers:
Reference 3e made to City Council Order No. 88-324 passed July 25,
1988 authorizing the extension Of the sanitary sewer on Stillwater Avenue
to Rogan Road, and to City Council Order No. 88-357 passed August 22. 1988
authorizing the further extension of said sanitary sewer In a easterly
direction n Rogan Road for a distance of 200 feet. All work has been
completed as follows:
The Installation consisted of 367 feet of 10 inch PVC pipe and
one manhole on Stillwater Avenue. originally petitioned by Miramar
Properties t0 serve a new motel developaent, and an additional extension
of 202 feet of 8 Inch PVC pipe and onmanhole in easterly direction
on Hogan Road to serve automobile lubrication -service facility located
on Hogan Road as petitioned for by Richard Been. The total actual cost
of the sewer installation was $29.061.42, which compares favorably with
the original estimate of $28.600.00, reflecting an overrun of 1.61%, and
which would result in the adjustment of the estimated assessments as
follows:
Estimated Final
Name Assessment Assessment
Miramar Properties. Inc. $3.780.00 $3.840.98
Daigle oil Company 1,720.00 1,747.75
City of Bangor 4,400.00 4,470.99 (to be deferred)
Richard Bean 4,400.00 4,470.99
City of Bangor 14,300.00 14,530.71
Total $28,600.00 $29,061.42
Miramar Properties previously prefunded their estimated share of
$3.780.00, and Richard Bean prefunded the entire share of the Regan Road
including that benefitting land owned by the City of Bangor on the
corner of Rogan Rodd and Stillwater Avenue, in the amountof $8,800.00.
Me original Council Orders provided that Daigle Oil Cospany would be
assessed when the work was completed and the final cost was known, and
also provided that a Subordinate Agreement would beexecuted between the
City of Bangor and Richard Bean to Insure that if the City land is developed
and requires entry into the sewer, then Mr. Bean would be reimbursed 50%
of the cost of the Hogan Road sewer by the City. Consequently, it is
-1-
89-2D1
recommended that Miramar Properties, Inc. be billed for the additional
overrun ,went of $60.98, that Daigle Oil Company be assessed in the
immune of $1,747.75, and that Richard Bean be assessed for the overrun
of $141.98 covering his project and the vacant city land. It is further
recommended that a Subordinate Agreement bee cuted to provide for the
repayment to Mr. Bean in the a of $4,470x99 at such time as the
City of Bangor land Is developed.
Plane showing the proposed sewer extensions are on file in the
Office of the City engineer.
Respectfully submitted,
JTA:JkP John T. Frawley,
City Engineer