Date 12/l D/90 Item No, 91-33
Item/Subject Accepting City engineer's Report - Final Cost of Sanitary Sever
Ext. to Martel Mobile dame Park on outer Hammond Street
Responsible Department: Engineering. _
Commentary: -
This report covers the actual coat of the sewer extension to the
Nortel Mobile Home Park on Outer Hammnd Street, which was
completed ata cost of $28,300.00, substantially below the
original eat Lee to of $50,000.00.
This Order should be referred to the Fimnce "Comnittee,and advertised
for a public hearing to be held at the next City Council meeting,
at which time ,it should be ready for passage. - -
Oepartmsne Nea6
Manager's Comments: —TT�IS
1IAILIC HE6PUA3Y6- r gra P -TOF 71`C77rTo,%,D
coy ef.wi
Associated Information:© /.
Budget Approval: lik_
Fina elDi,e
Legal Approval
City Sa4Tfmr
Introduced For
0 Passage
VIFirst Reading Page _ of
eferral &
91-33
AerignedbfowNm Saxl. December 10, 1990
CITY OF BANGOR
(TITLE.) (JgrNpX, ,Accepting City engineer's Report_ - Final Cost of Sanitary Sever
Emtension to the Martel Mobile Home. Park on outer Hammond Street
............. _._........... __.._ .._._.. _.. _. .....1.....
By W City Ceased ads CAy of Beaver:
TWT the attached report of the City Engineering showing the actual cost
and recommended assessments for the extension of the sanitary a on OuteHermannEamnn Street toserve e the Martel Nubile Nome Park be and hereby is accepted;
and be it furtherr e _ .
ORDERED,
TMT said assessments be levied or deferred as recommended in said report.
In City Council Decenber 10,1990
Refuted to Pinions Committee
C y Cletk
IN CITY COUNCIL
December 26. 1990 _
Passed
ITY tWE&K
91-33
O ROER
Title,
Mcepting City Engineers Reyoi[,,...
final coat of Sanitary Sewer Extension
t0 the Martel Mobile Home Park on nutter
......................................
Hamn�ojpdC/�/f�t��� {�
aoun i bn
91-33
CITY OF BANGOR, MAINE
Engineering Department
December 4, 1990
To the Municipal Officers
Reference Is made to City Council Order No. 90-250 passed Tune
25. 1990, authorising the extension of sanitary sewer
service on Outer
Hammond Street to serve the Martel Nubile Bone Park.
All work has been completed, and final costs have been determined,
as follows:
The installation consisted of 1,100 feet of 8 inch pipe and 4
manholes, extending in anortheasterly direction from the existing
sanitary sewer located o the easterly aide of the H�ond Street Bulge
to Wier Retraced Street t
adjacent to the southerly property line of the
VFW Rall.
The actual east of the sewer Installation was $28,300.00, which
1s substantially lees than the original estimate Of $50.000.00. One of
the major reasons for the cost underrun is that ledge was not encountered
as anticipated in the original estimate. Consequently, the total actual
oat is pro rated against the properties benefitted in the ease
ratio as
contained in the original report to the City Council, with the actual
assessments to be as follows:
Martel Trailer Park
1335 Harwond Street
$16,980.00
Dominic Inflamer
1337 Harwood Street
1,698.00
Blanche Dore
1408 Herwand Street
11698.00
veterans of Foreign Wars
1368 crossed Street
1,698.00
Bertille Martel
1336 eeosond Street
11698.00
Charles Mason
Ha®ond Street Bulge
2,264.00
Sidney Epstein s Kenneth Sermon
Trustees of Pransway Realty Trust
2,264.00
$28,300.00
-1-
The extension of the public sever was necessary to abate a
serious health problem created by a malfunctioning septic tank system
which served the Martel Trailer Pack9 bath the Department of Melton -
mental Protection and the City Code Enforcement Office had previously
directed that the trailer park be connected Into the City sever system.
In accordance with the original report to the City Council, Mr.
Martel deposited the sum of $50,000.00 with the City. to cover
the entire
e
set of thea r installation, and the Veterans of Foreign Wars and
Charles Mason agreed to pay their share of the a meat upon the
completion Of construction and the acceptance of the final cost report
by the CIry Council. The owners of the other properties which benefitted
indicated that they were act in favor of the sewer extension, and were
advised that their a amens would be deferred until they requested
entry into the sewer, asses
not longer than ten years, with ten percent
annual Interest added to the unpaid balance during, that period; upon
Payment of their assessments, Mr. Martel world be reimbursed, including
theaccrued interestessSince the actual construction cast was much
leas than the original estimated, the City Engineer would propose to
request that they reconsider their Original request for deferral. In
any event, Mr. Martel would be immediately reimbursed the a= of
$21,700.00, being the difference between the original estimate and
the actual cost, and would be reimbursed the full amount of the other
assessments at such time as LY are levdE1 and paid.
It is recommended that the a menta be levied or deferred
s described above,and that Mr. Martel be reimbursed for the unexpended
portion of his deposit.
Plans showing the actual sewer installation are on 81e in the
Office Of the City Engineer.
Respectfully submitted,
JTP:1kP IoM T. Prm' Y,
City Engineer 444