COUNCIL ACTION
Date 4-27-92 Item No,..
Item/Subject: Order, Accepting the 1992 Combined Sewer Overflow
Capital Projects Plan.
Responsible Department: Engineering
commentary:
The City's existing Consent Decrees with the State of Maine and the
United States Government require an on-going program of sewer
renvation and separation. In general, the annual commitment is
rrently in the range of $2 Million per year. This requirement will
remain in place until the City has completed and the appropriate
regulatory agencies have accepted a CSD Facility Plan which is
currently being prepared by our consulting engineers.
We have prepared a proposed program of work for this year. A list of
the proposed projects is attached. The total cost of the program is
w
estimated ea 81,740,000. Of this, $740,000 of prior s capital
r
fund and other resources have been identified for these purposes. The
remaining 81 Million must be borrowed as an element of our proposed
August, 1992 bond issue.
Approval of these projects will allow us to begin the process of
developing the nary bond orders and authorizations and will allow
the Engineering Department to take the necessary steps to issue bid
documents. It is our desire to begin theseprojects as moon as
possible in order to complete them earlier this year and avoid the
problems of projects continuing over the winter.
The Finance Committee has reviewed and approved this program
spa
Manager's Comments:
-------------mems: -------------------------------------------------
I would also request your approval
22
City Manager
Nssoclated Information. Ortler, Meme from Finance Dl recto Pro' t
list.
SUCget--------------------------------------------- ---- __ ___________
Approv
n__--________
ce
_________________________________ Fi --- Director
________________ ____-___----__
Legal Approval:
--------------------
City Solicitor
92-234
Moped to Conneilor Sas1 Aril 27, 1992
CITY OF BANGOR
(TITLE.)(TITLE.)4tl11
/gyprDert .Ac.c.. "tance
of the 1992 Combined Se . we 11 r Ov flw Capital
.....
Projects Plan
By the City Commit of W Oft NBawdr
ORDERED.
TUT
The 1992 Capital Projects Plan far the Combined Sever Overflow projects totalling
$1,740,000 in estimated casts is hereby accepted and adopted
In City Council April 27,1992
Passed
4 Clerk
92-234
ORDER
Title,
Acceptance of the 1992 Combined
Sewer overflow Capital praj act Plan
pppp\\ N fined to •••• '
........ ......unci..... i
Oouncilman
92-234x1
aTv of
PMAINE
e4MOOR 4,N
Y FINANCE DEPARTMENT "4,20AKIJ WO
1Mn Guam,.,,. Fm..w.
April 16, 1992
iI
:B3®rd A. Barrett, City Manager
John Qwrtererp, Finance Directoron1992 C50 Cstruction Program
m MCI, Acting City Egineer, hon suhlttM pT hie C30 canstruction m
ou 1992. It is his intention to begin construction this sir. Its
total coat of the projects is $1,740,000. 3 have identified approximately
$740,000 of prig bort borrowings mai other sewer ressutea Tlch Could be
ocumittecl to thea pttejects thereby reducing the amount to be borawed to
$110001000.
I weld anticipate adding the $1,000,000 to the July 14, 1992 issue Tach
would settle on August 3 or 4, 1992. Reports are that the Psderal Rexene
will ret be raisirg interest rates amtil the third quarter, therefore, tle
city would be able to borrow before rates begin increasing. As you are
ansae the country Is experiencing the lowest interest rates in yeare as
it would to the lag team benefit of the city to take advantage of these
rata now.
Given the hew IRS rules especially on relmbualng a Renes incurred batters
Ends are ieseed, we will d to begin the process of public hearings and
Council action m a band oadmr and other onlers for the projects. I would
like to hae Chris Fossil start to draft the bad and other feCerelly
required orders for presentation to the Council, Concurrent with their
discussions on the omits of the projects.
This item will reed Finance Cc®i4tee review ad a recamdetim to the
Council before proceeding. J
v
92-234
City of Ban]or, w
Engineering BROthrent
1992 � Pr m - PJbaecrlpti
7% 1992 seer pxeayam is a con d tlm: of major upgradbV and dmprw®v:t
Of tic City's sewer sya ae reguixed by L BPA!lament %)neaomt. Tdase
Ivo jor co��east oaf n1198�aM Mare tic cbjec of elimviat ng
iMo tla ae..er syst®4. y t of the a doom to date dmolaes�ratim of
sanitary artl s[aao sewer sya do th a aurae Of t City xitich lwv beat
idarRiEted through air ee•.er m toring PraFmi, as having fila higl t dsq e
of exf ,s x0141 en trg tla syatan. puler wtak baa irn0lved la -cocci
Or rel'^` otlmsw.,rin of major sahunk 1Lae co elhninate i 'iltra fnc Tla
projeara to be v:in 1992 will to similar in nedae aril irclvda the
follaahg:
Axetfc Bank Sswx Smaratim:
'Ate groJect will imolve tie sepazatfa: of sewer }fines in the ear Iy
half of the a ngox Gazdme area, and is a oontimutfon of pJj
cow4+lehal in Bangor Cardene aM dish ag Cairlga ova t}m poet two
yassa. Tle PrOjcot will £mmive appmrdnm y 3,400 lineal feet of res
s tart' s harallation, 200 lineal feet of stomn ever, arc! 21 new
naNales. 1kNitimal projects will be do the Arctic Avok
Suteectim: in fubsse years with tie oblecttve Of elhdnatug
Brook M to the Mn&wkmg Strain in 1995.
'Aral estima cost: $425,000.
hlmdHWcook Se +'N Plass N
TLis p Je is also a cont tlrn of proviam ewu sties: projects in
Tie Naarbudaoolc a:Eseeticn. W k for 1992 will d lve sePa Uan of
exieti.rg wrbired asexs On Elm Street aM Preset Avemm bet
Stillvster A acrd Grove Street, including 4,100 lineal feet of rsa
smrttary sewer, 21 new m Olne, and rsavectia: of iMividual douse
sxv tO tl oav s tart' !lura. The weadxdmmk Subaaiion is one of
tla lar$ ; eaoec sulsectione within the city, aryl wlll rs9uira aevaal
noxa SBais of major p OJO= to cmpiste the sw,..s.a,..,, when sem.:.,.,
is cageted, a considerable amamt of �tioo of ewtraneons water
will be aldmine from the syr .
'ental eatLmtad ash $700,000.
Oiin Rend Sorer ne.o..�..
'Ate project im 01v repOacamnt of a.g.�y 1,000 feet Of existing
8" Ba toW seer on the section of Olin Woad north of 1-395, `dtich Pe
in Pox etrvctural condition and has draiegnate capacity due to recent
duvelcp�. The p Jett wlll also hclude rep� of an etlditiaal
3,000 lin 1 fret of a ti:g le. trunk sager srnvth of I-395, which is in
vary pox oon& im and contribatea a cofaiAerable aaamt o£ infa-
tration. ands project mist be this yes¢ ptix to the Plaruad Pvrir
con u ion project on Olin iaaad.
Tbtal estimated coat: $475,000
92-230
Birch Street Se 1+mlacme tt
This involves reclacurent of approximately 900 lineal feet of extrevely
deteriorated sever lire on the lower section of Birch Sheet between
State StrSst and0auoock Street. 1 sewer lire also arTtributes a great
deal of extcaneaus venter, and has experienced four structural faflurxs fn
the last 15 months. 90ase fair have resulted in heaeeent flooding in
the reighborbeod.
ibfal estimated mat: $90,000
In addition to the conatruxio: projectsounired above, we will reed to
begin survey and pre indnary study w in additiaul subsea i s histUfled
fn the an -going G study curmently being done by �-idii.l. minae study
areas incluse:
19th Street
This subsection cuaently has a CSO at the Kenduaimsg Stream. Pielimtmry
survey and study Beck cc Qlcte l In 1992 w l be used to paefonn design
t for a 1993 wretmecio: project. NMir:.m.i construction projects
through 1996 will evenGally result in the elimination of the M.
Tbfal estLiatel cont: $25,000
Airoort Seuus
The Airport Serer SbbSsCUOu wire esaterly from the Airport to the
ysd:skaag storm: and also includes the nese Capehar't area. Preliminary
flaw ma:iror3ng panfoarsl to data fndfratas that many Areas of this
subsection Main sewer 1Lae that are fn mM mely poor structural
ooMition and contribute excessive amounts of infiltration. Survey and
Study w to be wdectaken in 1992 will be need for design
for a 1993 caatrvctio: project.
Total estLneted cost: $25,000
Total oust, 1992 sewer projects: $1,790,000
92-234
CITY OF BABOON, MAINE
Engineering Department
Match 31, 1992
ESTIMATED COSTS - 1992 SEWER
PROJECTS
AIRPORT SEWER
80,
81, 82 Fiscal d legal
$ 1,000
86
Survey 6 Design
22,500
90
Engineering Administration
1,500
$25,000
ARCTIC BROOK SEVER SEPARATION
80,
81, 82 Fiscal d Legal
$17,000
86
Survey E Design
25,000
90
Engineering Adm.
3,500
92
Testing fi Inspection
20,250
95
Construction
342,250
99
Contingency
17,000
$425,000
BIRCH STREET SEWER REPLACEMENT
80,
81, 82 Fiscal 6 Legal
$ 3,600
86
Survey d Design
6,300
90
Engineering Adm.
900
92
Testing 6 Inspection
4,500
95
Construction
70,200
99
Contingency
4,500
$90,000
FOURTEENTH
STREET SEWER SEPARATION
80,
81, 82 Fiscal d Legal
$ 1,000
86
Survey 6 Design
22,500
90
Engineering Adm.
1,500
$25,000
MEADOWBR00K SEWER SEPARATION, PHASE 4
80,
81, 82 Fiscal d Legal
$28,000
84
AN Acquisition
11000
86
Survey a Design
45,000
90
Engineering Adm.
5,000
92
Testing 6 Inspection
35,000
95
Construction
558,000
99
Contingency
28,000
$)00,000
-1-
ODLIN ROAD SEWER REPLACEMENT
92-234
80,
81, 82 Fiscal & Legal
$19,000
86
Survey d Design
31,000
90
Engineering Adm.
4,OOD
92
Testing E Inspection
20,750
95
Construction
385,250
99
Contingency
15.000
$4)5,000
TOTAL: $1,740.000
-2-