HomeMy WebLinkAbout1995-07-24 95-348 ORDERCOUNCIL ACTION
Date: July 24, 1995
Item No. 95-348
Item/Subject: Order, authorising a Change Order to an Existing Contract with
Hughes Brothers and G.R. Adams, Inc. for Underground Oil Tank
Removal at Bangor International Airport
Responsible Department: Airport
Hughes Brothers and G.R. Adams, Inc. have performed a number of underground
storage tank removaland replacements for the airport over the last several
Fears. Additional work is required this scanner to remove and replace a
number of fuel storage tanks for the boilers at the domestic and
International terminale. These tanks are located in sensitive areas adjacent
to the terminal buildings and space used by our tenants. Aa a result, it is
essential that the work be done in a timely and coordinated fashion.
To date, the airport has bean extremely pleased with the work of Hughes
Brothers and G.R. Adams, Inc. As a result, upon completion of preliminary
design work by our architects, Woodard and Curran, Hughes Brother was
requested to provide a proposal for performing this work. Our architect
submitted an estimate for the work at $168,450. Hughes Brothers submitted a
price of $153,050. The total amount of the contract with Hughes Brothers to
date Is $381,318.
The possibility of having this work completed by change order was discussed
with the Finance Committee at its last meeting. The committee concurred with
recommendation of airport management that the change order be approved so
that work can commmence and be completed in a timely and coordinated fashion.
Given the size of the change order, it is presented to the full Council for
its comurreme.
u3a.:WIXOMnrel_
Manager's Commmantss
I concur and reocamend approval.
Order, Letter from Richard S. Cattails, Letter from Woodard and Curran.
Budget � Approval
J%S
Legal Approvalz
A 6M,CITY °
Int educed For ° O
passage
First Reading page_of_
Referral
95-368
Assigned to CommEm Woodcock duly 26, 1995
CITY OF BANGOR
(TRLL.) Uffrbgr, Authorlsing.a Change Order to an Existing Contract
with Hughes Brothers and G.A. Adams, Inc. for Underground 011
Task Removal at Bangor International Airport
By du my OomuH Of Qu Otty ofDeaver:
ORDERED,
THAT there is hereby authorized a change oder in an
existing contract with Hughes Brothers and G.R. Adams, Inc. in
the amount of $153,050 for removal of underground fuel tanks at
Bangor International Aikport. This change order covers
additional tank removals related to the international and
domestic terminal buildings.
Ix CITY- COUHCIL 95-348
July. 24,-1995 O R D E R -
Pa d
Title, Authorising a Change Order to
CITY CLBBF an Hoisting Contract with Hughes Brothers
d G.R. Adams, Inc, for Underground Oil
Wank 1�emtiaaY iC Airport .. .
Assigned to ........
Councilman .
95-348 sq -
Richard S. Catteller Inc.
Real Estate & DeveloRmmnt -
SNlE3M
pYE CUNBENANo nACE
BaNfiORM00i10L5D19
July 11, 1995
Mr. Bob Ziegelaar
Bangor International Airport
287 Godfrey Boulevard
Bangor Maine 04401
As you are aware, Hughes Brothers and G. R. Adams Inc. have performed the previous
underground storage tank removal and replacements for the Airport during the past few
years. The last of the Current contract work, the removal of the gasoline tanks at the
service station on Maine Ave, is scheduled to be accomplished this summer. The additional
work that needs to be accomplished this summer is the removal and replacement of the
fuel storage tanks for the boilers at the domestic and international terminals.
The design has been completed by Woodard and Curran and has been reviewed by you and
your staff. Woodard and Curran has also provided an estimate of 8187,450.00 for the
cost of the project. We have a good experience base from the previous work at the airport
so we can be confident with the accuracy of the estimate.
pursuant to our request Hughes &others submitted a proposal for the project if performed
as a change order to the existing contract. Their proposal was for 9153,050.00. A
comparison of their proposal to Woodard and Curran's estimate and associated discussion
is in the June 5, 1995 letter attached from Brent Bridges to myself.
In as much as we have had an excellent experience with the contractors in their
performance of the previous aimed current contracts, and: in as much as this project is in a
high traffic area and requires an accurate and efficient performance of the removal and
installation, and; in as much as the proposal by the contractor is approximately 10%
below the adjusted estimate of cost; it is the recommendation of Woodard and Curran and
myself that we issue a change order to the existing contract to perform the work.
If it is decided that we should proceed in this manner the contractor is available to begin at
your convenience.
If you have any questions please give me a call
Yours truly,
Richard S. Cattelle
CONSULTING
rm aIS-309n IN PPR:941,3085
95-348 ?"5
WOODARD `- CURRAN
June 5, 1995
Dick CaveBe
t Cumberland place
Suite 312
Bangor, ME 04401
RE. BIA Domestic& International Anivals Terminal Tanks
MUM
We have received and reviewed the Hughes Brothers estimate for the tank removal, abandonment,
and replacement at the Domestic and International Arrivals Terminals at Bangor International
Airport. The total cost of thepmject submitted by Hughes Brothers is $153,050.0s) The estimated
unit prices are within our expectations baud on the estimate of $187,450.00 that we had given to
you previously.
Total costs were based on thequantities in the Bid Tab, except for Item 6, Removal and disposal of
N2 fuel oil or diesel fuel sludge in underground tanks. It was assumed during design that the
contents of the existing tanks would have to be removed and disposed of. At the fine of design,
all Links were nearly full and the estimated quantity for disposal was 21,000 gallons. In order to
save money and avoid waste, theop6r11a1 solution Is fM Bl to r ove as much fuel w they cart
from [M tanks prior to the start of Ibis project leaving a small residual to be pumped out and
disposed of. The estimate from Hughes Brothers anticipates this situation and the quantity of fuel
has been changed from 21,000 gallons to 2,000 gallons in their bid and should be modified in our
estimate as well. That change would reduce our estimate down to $168,450.00:
Please let us know if this solution is feasible for BNA. Ideally, Hughes Brothers would like to scan
as early as rest week and dig safe and needs 72 hour notice.
If you have any questions, please let me know
M
Very holy yours,