HomeMy WebLinkAbout1995-01-23 95-82 ORDERCOUNCIL ACTION Item No.95-82 Date January 23 1995 Item/Subject: Authorizing City Manager to Accept Settlement of City of Bangor Wastewater Treatment Plant Claim -- Liquidated Damages for Late Project Completion Responsible Department: Legal In February, 1993 The Holden Company, a subcontractor on the City of Bangor's wastewater secondary treatment plant project, became insolvent, and defaulted its subcontract. The company later filed for bankruptcy liquidation under chapter 9 of the federal bank- ruptcy statute. As a result, a small amount Of the original contract work on this project ($29,585.00) remained incomplete a of the June 30, 1993 scheduled project completion date. The work concerned s w not completed until September 20, 1993. Due to the late projectfinish, which required the City to extend its supervision of the project by an additional 68 project days', the City's Engineering Department incurred a estimated $19,000.00 in additional personnel costs. The attached Council Order would authorize acceptance of a settlement offer from Connecticut Indemnity Company and Harvey Construction Company, which would reimburse the City's additional costs. Department Head Manager's Comments: A,¢ '7%llJ �rl(1�LM1lap*X UJLIYI 0& Gw Z% 4`fla r� LrL �/. _ n n'a Q/0 —Finance —Director cies Spttor4 Introdu �d For C& wxT- =� Passage First Reading Referral Page i of 2 C.4tUVA&U.In City Manager Associated Information: Order —Finance —Director cies Spttor4 Introdu �d For C& wxT- =� Passage First Reading Referral Page i of 2 95-82 Anigeedm Cmuncilor Tyler Jauvary 23, 1995 CITY OF BANGOR (TITLE.) Wrbtr, _... Authorizing City Manager to Accept settlement of City of Bangor Wastewater Treatment Plant Claim -- Liquidated Damages for Late Project Completion BY He Qh Cm 1of Ae Cft of Ransom TEAT the City Manager is hereby authorized on behalf of the City of Bangor to execute all releases and other documents necessary to accept a $19,000.00 settlement of the City of Bangor's claims against Harvey Construction Company and Connecticut Indemnity Company as performance bond surety for The Holden Company, arising out of the late completion of the City's wastewater secondary treatment plant project. All releases and other documents executed by the City of Bangor shall be in a form approved by the City Solicitor. 95-82 IN CITY COUNCIL 0 R D E R January 23, 1995 Passed Title, t Autfioilzln .C1 y Nan d Accept Settlement CITY CL£ Of City of&Bangui iVesLeve[eiTxee[men[ Plant Claim - Liquidated Damages for Late Project FAMPlAtttIcu/j%............ .. ��. /��..} .... . Aulgned to ..... �yY.•4...F r:X r<- .F....Co.un...ci..'..n.. V U lma 0