HomeMy WebLinkAbout2017-08-14 Infrastructure Committee Minutes
Infrastructure Committee
Minutes
August 14, 2017
ATTENDEES
Councilors:
Gibran Graham Dan Tremble Benjamin Sprague
Sarah Nichols David Nealley Cary Weston
Sean Faircloth Joe Perry Joe Baldacci
Staff:
Cathy Conlow John Theriault Dana Wardwell
Andy Rudzinski Richard May
Members of the Public:
AGENDA
1. Sewer Abatement Quarterly Report
Andy Rudzinski provide the Committee with an outline.
No Action Necessary
2. Stormwater Agreement & Easement: Bangor Housing Authority
Richard May and John Theriault briefed the Committee on the agreement and easement with Bangor Housing
Authority necessary to begin the Old Capehart Bioretention Cell Project in the Capehart Brook watershed.
No Action Necessary
3. Agreement: MDOT Modification 1 to WIN #20895.00, Ohio Street & Fourteenth Street – Additional
Funding
John Theriault explained Maine Department of Transportation increased funding for the project. A modification to
the original agreement would need to be executed by the City Manager.
Motion Made and Seconded, Unanimous Vote to pass.
4. Discussion: Sidewalk Grant
The City of Bangor is applying for Grants through Maine Department of Transportation for sidewalks
on:
Hogan Road
Buck Street
John Theriault outlined his intention to apply for MDOT grants for sidewalks on Hogan and Buck Street.
Motion Made and Seconded, Unanimous Vote to pass.
1
5. Discussion: Rezoning 73 Harlow Street, City Hall & Easements for Retaining Wall
John outline steps necessary for the upcoming City Hall/Park Street Retaining Wall Project. Rezoning would be
required to allow for the expansion of parking and a smaller building in conjunction with the project. The project
would also require an easement with the Unitarian Universalist Society, who abuts the work site area.
No Action Necessary
John Theriault added another item that was not previously on the Agenda, as it was presented to him prior to the
meeting. An easement would need to be executed between the City of Bangor and Emera for work Emera
proposed on Valley Avenue and Kenduskeag Avenue, under the interstate. The work would consist of replacing
existing poles on high transmission lines.
No Action Necessary
Meeting Adjourned.
2