HomeMy WebLinkAbout2015-07-27 15-256 ORDERCOUNCIL ACTION
Item No. 15-256
Date: July 27, 2015
Item/Subject: ORDER, Authorizing Execution of a Utility Receivable Agreement for Maine
Department of Transportation Local Project — 19311.00, Webster Avenue Bridge #5796
Responsible Department: Engineering
Commentary: This order would authorize the City Manager to execute a Utility Receivable Agreement
with the Maine Department of Transportation for furnishing and installing a gravity flow sanitary sewer
line in conjunction with the removal of Webster Avenue Bridge #5796.
The Maine Department of Transportation has identified the locations of existing utility facilities owned
and maintained by the Utility and lawfully installed within the limits of the public highway right-of-way
and the impact limits of the Project that must be relocated to accommodate the Project. The City share
$55,781.00.
As part of that project, the City would need to enter into a Utility Receivable Agreement with the Maine
Department of Transportation.
Manager's Comments:
Associated Information: Councilor Order and Agreement
Budget Approval:
Legal Approval:
Introduced for
X Passage CONSENT
First Reading
_ Referral
John Theriault, P.E.
Department Head
City Manager
Finance Director
V
Page _of_
15-256
.j
JULY 27, 2015
Assigned to Councilor Blanchette
CITY OF BANGOR
ER, Authorizing the Execution of a Utility Receivable Agreement for Maine
Transportation Local Project — WIN #19311.00, Webster Avenue Bridge
Manager is hereby authorized and directed to execute an agreement with the
lent of Transportation for the following:
able Agreement with the Maine Department of Transportation — In
th the Webster Avenue Bridge #5796 Improvements
reement is attached.
IN CITY COUNCIL
JULY 27, 2015
PASSED o
CITY CLERK
MAINE DEPARTMENT OF TRANSPORTATION
UTILITY RECEIVABLE AGREEMENT
(MaineDOT Use Only)
Project Location: Ban or Estimated Agreement Amount: $ 55,781.00
State WIN #: 019311.00 Vendor Customer #:
Federal Aid Project #: AC -IM -1931 (100) Agreement Begin Date:
Forecasted Agreement End Date: June 1, 2016
THIS AGREEMENT, in duplicate originals entered into this day of ,
between the Maine Department Of Transportation (hereafter the "Department") and City of
Bangor, duly authorized and existing under the Laws of the State of Maine and having an office
in the City of Bangor, County of Penobscot (the "Utility") (the Department and the Utility are
collectively referred to as the "Parties").
1. The Department is implementing a transportation project identified as "Federal Aid Project
Number:AC-IM-1931(100)E;WIN: 019311.00 (the "Project") for highway improvements in
the City of Bangor, Penobscot County;
2. In connection with the Project, the Department has prepared plans and specification for the
Project that resulted in the following determination:
X The Department has identified the locations of existing utility facilities owned and
maintained by the Utility and lawfully installed within the limits of the public
highway right-of-way and the impact limits of the Project that must be relocated to
accommodate the Project (the "Affected Facilities");
3. The Affected Facilities consist of Sanitary Sewer Line;
4. The Utility has prepared and provided to the Department the scope of work necessary for
relocating or installing the Affected Utilities (the "Utility Work") and the estimated costs
associated therewith, which are outlined in Appendix A, attached hereto and made a part
hereof. The costs associated with the Utility Work are the sole responsibility of the Utility.
Page 1 of 7
Receivable Agreement, Version 4-1-2015
5. The Parties wish to establish a process for including the Utility Work in the Department's
construction contract for the Project.
NOW, THEREFORE, the Parties agree as follows:
6. Plans, Specifications and Estimate:
a. The Utility shall, at its own expense, perform and provide all engineering, design and
related services related to the Utility Work necessary to enable the Department and/or
its consultant to generate construction plans, specifications and an estimate of
material quantities for the Utility Work to be included in the Project contract. The
Utility will be responsible for locating and recording the location of all Utility Work,
including services and other appurtenances within the Project area. To the extent
possible and consistent with laws, practices and policies of the Department and the
industry, the Utility Work shall be performed in accordance with the plans and
specifications provided by the Utility and, if applicable, the most recent version of the
Department's Standard Specifications.
b. All plans shall be on sheets of the same size used by the Department and be
reproducible by black and white printing. Specifications shall be on 8 '/2 x 11 -inch
paper, suitable for binding with the Department's specifications. The estimate of
quantities shall be in the form prescribed by the Department. In the event of field
changes to the Utility Work, the Utility shall prepare any additional plans and
specifications and the Department shall prepare a Project change order and amend
this Agreement incorporating any changes therein. All plans and specifications will
be marked with the Federal Aid Project Number referenced in this Agreement.
c. The Utility will provide the Department with the plans, specifications and an updated
estimate as described in Appendix A no later than one month prior to the scheduled
advertise date for the Project.
d. The Utility shall be responsible for obtaining a Utility Location Permit from the
Department in accordance with Title 35-A M.R.S.A. Chapter 25 and for recording the
location of all utilities in a manner and form to be specified by the Department.
e. Opt -Out Approach: The Department will prepare the Project contract documents to
include the Utility Work specified in Appendix A as an opt -out bid option. The
Utility Work items will not be used as a basis of contract award. Bidders will be
required to bid both the Project work and the Utility Work, with the low -bid for the
Project work used as a basis of contract award. Upon the Department's selection of
the low -bidder for the Project (the "Selected Project Contractor"), the Utility agrees
as follows:
i. If the Selected Project Contractor's submitted bid for the Utility Work is no
more than 15% over the total estimated amount for the Utility Work included
Page 2 of 7
Receivable Agreement, Ver 4.1.15
in Appendix A, the Utility agrees to have the Utility Work included in the
Project contract. The Utility Work will be paid for by the Utility, and any
changes that increase the Utility Work estimate or amount will be paid for
through a written modification of this agreement approved by both the Utility
and the Department.
ii. If the Selected Project Contractor's submitted bid for the Utility Work is more
than 15% over the estimated amount for the Utility Work, the Department will
provide the Utility with the applicable bid prices for the Utility Work from the
Selected Project Contractor. Within 48 hours of such notification, the Utility
agrees to notify the Department of its authorization to include the Utility
Work in the Project contract or its decision to accomplish the Utility Work
independently.
1. When the Utility Work is included in the Project contract, the Utility
Work will be paid for by the Utility, and any changes that increase the
Utility Work estimate or amount will be paid for through a written
modification of this agreement approved by both the Utility and the
Department.
2. If the Utility elects to perform the Utility Work independently, the
Department will remove the Utility Work items from the Project
contract, and the Utility agrees to accomplish the Utility Work in
accordance with their plans and specifications in a manner that, in the
opinion of the Department, does not adversely affect the Project's
construction operations or cause delay in the Project's construction
schedule.
7. Inspection:
a. The Utility shall be responsible for providing all engineering and inspection
associated with the Utility Work including computing quantities for payment and
other incidental and related work unless otherwise stated herein. By the end of each
work day, whenever Utility Work is performed, the Utility will provide the
Department's on-site representative with an itemized summary of all the Utility Work
completed.
b. The Department shall provide inspection of the quality and compaction of backfill
installed in connection with the construction contract, excluding bedding and other
special backfills and materials used in the installation of the Utility Work.
c. If the Utility Work is included in the Project contract pursuant to Section 6.e. above,
the Utility agrees to the following:
i. Should the Utility find the Project contractor's materials or workmanship to
be insufficient in any way, the Utility agrees to inform the Department's on -
Page 3 of 7
Receivable Agreement, Ver 4.1.15
site representative as soon as possible, but no later than the end of the day in
which the problem is identified.
ii. As administrator to the construction contract, the Department's on-site
representative shall be responsible for authorizing all payments relating to the
Utility Work, issuing all directives to the Project's contractor and making the
final determination in the event of any disagreements.
8. Ownership of Completed Utilities: Upon completion of the Utility Work the Utility shall
assume complete ownership of, and responsibility for, the utility facilities installed in
connection with the Utility Work.
9. Claims: The Utility shall be responsible for the prompt review and settlement of any claims
arising from or related to the Utility Work or its impact on the Project.
10. Indemnification: The Utility shall indemnify, defend and hold harmless the Department and
its officers, employees, agents and assigns, from and against any and all claims, liability or
expenses, including but not limited to reasonable attorney's fees and litigation costs (the
"Claims"), to the extent such Claims are caused, or alleged to have been caused, by acts or
omissions of the Utility or any of its officers, employees, agents, representatives, supervisors,
contractors, subcontractors or consultants in connection with the performance of its
obligations under this Agreement. Nothing in this Agreement is intended or shall be
construed to waive any defense, immunity or limitation of liability that may be available to
the Department or the Utility pursuant to the Maine Tort Claims Act (14 M.R.S. § 8101 et
seq.) or any other privileges or immunities provided by law. The terms outlined in this
section shall survive any termination or expiration of this Agreement.
11. Buy America Requirements: This agreement is subject to the requirements of Buy
America in accordance with Federal Regulation 23 CFR 635.410 Section 1518. Specific
requirements are presented in MaineDOT Standard Specification Section 100, Appendix A,
Section 3.A., Buy America which are incorporated and made a part hereof by reference.
12. Subsequent Excavations and/or Installations: Except in the case of an emergency, the
Utility acknowledges and agrees to refrain from applying for a permit for the excavation of
the highway within the limits of the Project for a period of at least N/A years following the
completion of the Project, and agrees to make all necessary notifications to abutters and
occupants of the highway as otherwise required of any municipal government under the
provisions of 23 M.R.S.A. § 3351. In all cases, whether an excavation moratorium as
described above applies, or as in the case of Light Capital Paving projects where no
excavation moratorium applies, the Utility further acknowledges and agrees that all
subsequent excavations and/or installations within the right-of-way of the Project limits shall
be regulated and controlled in the manner specified by the most recent version of the
Page 4 of 7
Receivable Agreement, Ver 4.1.15
Department's "Utility Accommodation Rules" '
ules"' which are incorporated and made a part hereof
by reference. The terms outlined in this section shall survive any termination or expiration of
this Agreement.
13. Non -Appropriation and Termination: Anything herein to the contrary notwithstanding,
the Utility acknowledges and agrees that, although the execution of this Agreement by the
Department manifests the Department's intent to honor its terms and to seek funding to fulfill
any obligations arising hereunder, by law any such obligations are subject to available
budgetary appropriations by the Maine Legislature and, therefore, this Agreement does not
create any obligation on behalf of the Department in excess of such appropriations. In the
event of unanticipated impacts on the Project, such as, changes in the Project design, or a loss
in Project funding, or a delay in advertising or awarding of the contract, the Department may
postpone, suspend, abandon or otherwise terminate this Agreement upon thirty (30) days
written notice to the Utility and in no event shall any such action be deemed a breach of
contract.
14. Payment: If the Utility Work is included in the Project contract pursuant to Section 6.e.
above, the Utility agrees to reimburse the Department for the full amount of the cost of the
utility work. A detailed breakdown of the anticipated cost of the Utility Work is attached
hereto and incorporated herein as Appendix A. The Department will issue a final invoice
after all the Utility Work is complete, all quantities are verified and any required adjustments
have been made. The Department, at its sole discretion, may issue periodic invoices for
portions of the Utility Work as it is being completed. The final invoice will include any
remaining costs or credits. The Utility shall submit payment to the Department within 30
days from the invoice date.
15. Contact Information:
For the Department: For the Utility:
Name: Denver Small Name: John Theriault PE, PTOE
Address: 16 State House Station Address: 73 Harlow Street
August Maine 04333 Bangor Maine 04401
E-mail: denver.small@maine.gov E-mail: johntheriault@bangormaine.gov
Telephone: (207) 446-6419 Telephone: (207) 992-4249
Page 5 of 7
Receivable Agreement, Ver 4.1.15
16. No Relief of Responsibilities: Nothing in this agreement is intended, nor shall be
interpreted, to relieve the Utility of any responsibilities or duties imposed upon it by law.
IN WITNESS WHEREOF, the Parties hereto have executed this Agreement in duplicate on the
day and year first above written by its duly authorized representatives.
IN THE PRESENCE OF: City of Bangor
Witness
Witness
IM
Print Name:
Title
Duly Authorized
STATE OF MAINE
DEPARTMENT OF TRANSPORTATION
By: Wayne Frankhauser Program Manager
Print Name:
Title
Duly Authorized
Page 6 of 7
Receivable Agreement, Ver 4.1.15
APPENDIX A
PROJECT SCOPE
MAINE DEPARTMENT OF TRANSPORTATION
UTILITY RECEIVABLE AGREEMENT
City of Bangor
(Webster Avenue BR# 5796)
FEDERAL AID PROJECT NO. AC -IM -19310 OO)E
STATE PROJECT IDENTIFICATION NUMBER (WIN) 019311.00
Project Scope: This work shall consist of furnishing and installing a gravity flow sanitary sewer line as
shown on the plans as directed by the resident.
ESTIMATE OF UTILITY WORK:
ESTIMATED PAYMENT SCHEDULE:
Utility Payment Amount
Estimated
Invoice Date
Estimated
Unit
Item #
Pay Item
Quantity
Price
Utility Cost
/Unit
659.10
Mobilization
LS
$5071.00
801.17
8 inch PVC Sanitary Sewer line
LF/280ft
$125.00
$35,000.00
803.173
1 Sewer Manhole 4 foot Diameter
EA/Ca)3
$3,700.00
$11,1.00.00
Contingency
$4610.00
Total Cost:
$55,781.00
ESTIMATED PAYMENT SCHEDULE:
Utility Payment Amount
Estimated
Invoice Date
City of Bangor $55781.00
June 1, 2016
Page 7 of 7
Receivable Agreement, Ver 4.1.15