HomeMy WebLinkAbout2010-07-26 10-268 ORDERCOUNCIL ACTION
Item No.1 n � 6 g
Date: July 26, 2010
Item/Subject: Order, Authorizing Contract Amendment with Honeywell — WWTP Operations
Building Heating and Ventilation System
Responsible Department: WWTP
Commentary: In December 2007, Honeywell, as part of its technical energy audit contract,
submitted its report of projects for the WWTP facilities. Due to the efficiency of the plant
operations, the projects that were brought forward were more operational in nature. At that time,
the only project identified as a priority was the upgrade of the heating and ventilation systems.
Based on this direction, Honeywell developed a project to address the HVAC systems. Due to the
estimated project cost, the City requested Honeywell to reduce the scope of work to make the
project more affordable.
The currently proposed project would replace the current HVAC system at the WWTP's Operations
building. The current system is a low pressure steam system that was installed in 1968, which has
not only reached the end of its useful life, but does not comply with current life safety codes. In
accordance with the City contractual provisions, upon completion of the engineering and design of
the system, Honeywell administered a competitive bid process. Staff spent a significant amount of
time thoroughly reviewing the project scope, the process employed as well as the overall
reasonableness of the proposed pricing structure.
This order would authorize an amendment to our existing contract with Honeywell, in the amount of
$1,004,146 and allowing the project to be completed prior to the upcoming heating season.
Manager's Comments: This was reviewed by the Finance Committee and
approval 7/19/2010.
Department Head
Interim City Manager
Associated Information: Memos from Brad Moore and Honeywell, Open Book Pricing
Summary
Budget Approval:
nance Director
Legal Approval:
Solicitor
Introduced for
X Passage
First Reading
Referral
Assigned to Councilor - Weston
CITY OF BANGOR
July 26, 2010
(TITLE.) Order, Authorizing Contract Amendment with Honeywell - WWTP Operations Building Heating
and Ventilation System
By the City Council of the City of Bangor.•
ORDERED,
THAT the Finance Director is hereby authorized to execute a contract amendment with
Honeywell for the purpose replacing the WWTP Operations building heating and
ventilation system .
IN CITY COUNCIL
July 26, 2010
Motin Made and Seconded for Passage
Passed
<qtpr�14Q
DEPUTY CITY CLERK 5�0lq
10-268
(T1TLE9)_Ajjthnri zing Contract Amendment
with AnnP=11 WWTP Operations Building
Hpatine and Ventilatin System
Assigned to Council
10 `'6g
MEMO
July 12, 2010
To: Finance Committee
Debbie Cyr
Jim Ring
Fr: Brad Moore
Re: WWTP Operations Building Heating System
The Wastewater Treatment Plant, for several years, has recognized the need to replace the
heating and ventilating systems in the operations building. The heating system is a low
pressure steam system that was installed in 1968. The need for this replacement was
confirmed by Honeywell through the energy audit process. Most of the major components of
the heating and ventilating system are original and are in need of replacement
The City entered into a contractual agreement with Honeywell to proceed with final design and
implementation for the replacement of the heating and ventilating systems. The contract
defined the process for competitive pricing, allowable mark ups and open book pricing.
Honeywell completed final design, bid the project and submitted a final proposal. As a result of
the project cost, the City requested Honeywell reduce the scope to make the replacement more
affordable. Honeywell subsequently provided another proposal with the reduced scope. The
project was then advertized and CCB, Inc., of Westbrook, Maine, was the successful bidder and
would handle the general contracting and mechanical installation work. CCB, Inc., has been
providing construction services in New England for 63 years and staff agrees the company is
capable of handling the scope of work in this project. As a part of our review of the project and
the process Honeywell has used, staff contacted CH2M Hill as a sort of peer review. CH2M Hill
is very familiar with the wastewater treatment plant and the procurement process Honeywell has
used. CH2M Hill felt that Honeywell's proposal pricing is reasonable and the markups are in
line with typical values for this process.
Staff considered the possibility of going to a standard competitive bid process but concluded
that it would delay the implementation of the project and quite likely result in no cost savings.
Honeywell did go through a competitive process in selecting the general contractor.
Considering the current economic climate, staff believes the pricing received reflects the current
trend of low construction costs. Delaying the project to next year will be very likely more
expensive. Honeywell's proposal provides guaranteed pricing, which is defined as a firm fixed
price (no change orders) for the contracted scope of work. This is an advantage to the City on a
project with this complexity.
As mentioned above, Jim Ring and Brad Moore have had numerous conversations with
Honeywell representatives, primarily Jim Lucy. These discussions involved the contractual
agreement between the City and Honeywell, scope of work, the competitive bid process and
Honeywell's mark up for the project. Included with this memo is a letter from Mr. Jim Lucy,
dated June 17, 2010, summarizing the engineering and bid process for this project along with
the pricing summary provided by Honeywell. After discussions in house and with Honeywell,
staff recommends proceeding with this project at the quoted cost of $1,004,146.
10 "68
Honeywell
June 17, 2010
Mr. Bradley Moore
Superintendent, Wastewater Treatment Plant
760 Main Street
Bangor, ME 04401
Brad,
The following is a summary of the bid process Honeywell followed to develop the proposed
upgrades at the treatment plant. I have also enclosed our open book pricing summary consistent
with appendix B of Honeywell's contract with the City for technical energy audits and project
development. This open book pricing summary includes Honeywell's project costs with our
agreed upon contract mark-up for overhead and profit.
Background: In August of 2006 Honeywell was selected by the City of Bangor following a competitive
Request for Proposal bid process to enter into a contract to perform technical energy audits and develop
performance contracting projects for 42 buildings throughout the City representing 1,316,418
square feet. The project development contract entered into between the City and Honeywell
incorporated an open book pricing requirement that included a fixed mark-up for overhead and
profit. These mark-ups are 13% and 10% respectively on top of actual project costs.
The technical energy audits were broken into four groups including the general fund, airport,
school department and waste water treatment facilities. In December of 2007 Honeywell
submitted its technical energy audit report for the Waste Water Treatment Plant facilities. The
report included recommendations to reduce energy costs, sludge tipping fees and upgrade HVAC
systems to replace equipment at the end of its useful life and to meet current code standards for
ventilation in the operations building.
In March of 2008 Honeywell received feedback from the City on the recommended measures it
would like to proceed with for final design and implementation. Following the completion of the
final engineering and bidding phase Honeywell submitted its final proposal to the City in
November of 2008. Since this period of time the project has been delayed due to available
capital dollars. In an effort to reduce project costs the City and Honeywell have made
recommendations to value engineer and modify the selected scope of work to reduce project
costs within available funding levels. The current proposal is the result of those efforts.
Bid Process:
Honeywell's typical bidding practices are dependant on the availability of our internal resources.
For this project Honeywell will self perform the controls portion of the work along with project
management, administration and commissioning tasks. The controls portion is quoted, as
negotiated previously with the city, using our posted manufacturer's prices for equipment and
the hours and associated labor costs for the controls work.
Following the completion of final engineering and design drawings Honeywell administered a
competitive bid process for the scope of work excluding the controls and oil pre -heaters which
are manufactured and installed by the supplier. Five pre -qualified contractors were invited to bid
+ x:68
Honeywell
on the general contracting and mechanical work and three pre -qualified contractors submitted
pricing. The three responding bidders were:
• Sullivan and Merritt
• CCB, Inc.
• RTH Mechanical
The results of the bidding for the general contracting and mechanical scope selected in March of
2008 are as follows:
• Sullivan and Merritt Constructors- $1,022,200
• CCB, Inc- $750,000
• RTH Mechanical- $958,321
Due to the large variation in bids, Honeywell conducted post -bidding interviews to confirm that
each bidder understood the scope of work and required procedures for completing the work.
CCB, Inc. was the selected bidder on price and overall comprehension of the required work to be
completed.
Following the completion of the bidding and contractor selection all recent scope modifications
made by the City have been re -quoted by the selected contractor CCB, Inc. The following open
book pricing summary outlines Honeywell's project costs consistent with our project
development agreement. Due to project budget constraints and in an effort to work with the City
Honeywell has excluded a significant amount of actual hours spent on this project during the
engineering and design phase.
Please let us know if you have any questions or if you would like any additional documentation
regarding the bidding process.
Regards,
Jim Lucy
d i j
L •ry of
r µ I' Open Book Pricing Summary
alne Waste Water Treatment Plant
s -
�3.
06"M 6"t Army
W*ft
A. PCE
Lobo '"
'WWW"
'11911
y4vap....
v
Tot6tt
A. PCE
$ 88 14
240
$ 21.110
B NI&V
$ 8814
-
$ -
C TECHIENG controls eng
$ 50 07
-
$ -
D. Const Mgml
$ 9699
90
$ 8,722
Sub Total
$ 9699
458
$ 29,832
E Contracts
$ 9699
0
$ -
F Consultant
S -
36200
0
$ 36.200
G. Financial Specialist
$ 67,07
0
$ -
H. Ck>ncal/Adrnin
$ 44.71
0
$ -
i. Program Management
$ 8814
0
$ -
Sub Total
$ 88 14
36200
0
$ 36.200
J Travel/Expenses
$ 540
855
$ 540
Sub Total
$ 540
$ 540
Design Subtotal
$ 36,740
$ 66,572
Installation
�3.
06"M 6"t Army
W*ft
A. PCE
$ 88 14
24
B M&V
$ 8814
0
$
En�ineerin/Technica! Sub Total
24..._$
..................._Z_ 115
C Contracts
$ 96 99
0
$
D. ClericaVAdrnin
$ 44.11
0
E. Construction Management
$ 9699
458
$ 44,421
Project ManagemontlSite Leader
$ 79.49
0
$ -
Control Software Engineer
$ 74 18
175
$ 12 982
Control Technician
$ 8370
222
$ 18.581
Fitters
$ 7626
0
$
Commissioning
$ 7949
0
$
F. Program Management
$ 88 14
0
$
Pro ram Management Sub Tota!
855
$ 75,984
Material
$
Outside Purchase
S
$ -
Honeywell Mfg Posted Price
Material Sub Total
$ 29,009
$ 29,009
$ 29,009
$ 29.0091
Subcontractors
$
General Contactor
$ 523,841
$ 523.841
Oil Heaters
$ 5,400
$ 5,400
Controls Electrical Installation
$ 76,599
$ 76,599
S
$
$
$
$
S
$
Subcontractors Sub Total
$ 605.840
$ 605,840
Other itn lementation Expenses
1 Travel/Expenses
$ -
$ -
2. PerformancolPayment Bond
3 4,519
$ 4,619
3 Contingency
Other Implementation Expenses
$ 21,170
$ 25,689
$ 21,170
25.689 1
Installation Subtotal
$ 660,537
879
$ 738,637
Summary
Energy Audit Subtotal $ - $ 2,631
Design Subtotal S - $ 66,572
Installation Subtotal $ 660,537 879 $ 7 38.637
Total Direct Costs $ 660,537 879 $ 807,840
Mark-up Percent 13'i6 10"•41
Marko $ 196,305 '.
Total Project Price Less Financing $ 1,004,146
Capital Funding $
Total Financed Amount $ 1,004,146
Construction Interest $
TOTAL FINANCED PLUS INTEREST $ 1,004,146