HomeMy WebLinkAbout2010-04-26 10-150 ORDERCOUNCIL ACTION Item No. i A 1 5 0 Date: April 26, 2010 Item/Subject: ORDER, Authorizing Contract Award for Ohio Street Resurfacing Improvements II Responsible Department: Engineering Commentary: On April 7, 2010 the City received one bid for improvements to Ohio Street. The bid price was $486,319 - see attached bid tabulation. The Finance Committee will meet to review staff recommendation to award the contract to Lane Construction in the amount of $486,319 prior to tonight's Council meeting. This is an MDOT BACTS project that is locally administered. This project will be funded 90% by the State and the City will provide the required 10% local match. The contract award recommendation must be reviewed approved by the City Council as it is over $50,000. Department Head Manager's Comments: -�,r AnC rm"Aw �ll�ft''U ✓�Iil� i'���GY Gl 1`� til �Grl/Gr� . Interim City Manager Associated Information: Order, Bid Tabulation Budget Approval: Legal Approval: Introduced for X Passage First Reading Referral nce Director Page _ of _ 1.0 150 Assigned to Councilor - Weston April 26, 2010 CITY OF BANGOR (TITLE.) Order, Authorizing Contract Award for Ohio Street Resurfacing Improvements II By the City Council of the City of Bangor: ORDERED, THAT, Deborah Cyr, Finance Director is hereby authorized to execute a contract with Lane Construction, in the amount of $486,319 for improvements to Ohio Street. IN CITY COUNCIL April 26, 2010 (TITLE,)-A„thnrj 7A nZ Contract Award for Ob4Q etgeet- RPS„rfaring Taprovements II Assigned to Councilor bl� City of Bangor Bid Tabulation - Ohio Street Resurfacing Improvements II Bid Opening: 04/07/10 Lane Construction Ban or, Me Item Description Qty. Unit Unit Price Total Price 1 202.202 Removing Pavement Surface 23480 SY 2.05 48,134. 2 202.203 Pavement Butt Joints 175 SY 17.00 2,975.00 3 203.20 Common Excavation 300 CY 90.00 27 000.00 4 304.08 Aggregate Base Course - Gravel 200 CY 155.00 31 000.00 5 403.207 3/4" 19mm HMA 50 TON 140.00 7,000.00 6 403.210 3/8" 9.5mm HMA 2180 TON 76.00 165 680.00 7 403.209 3/8" 9.5mm HMA sidewalks 290 TON 150.00 43 500.00 8 403.211 HMA Shim 100 TON 97.00 9,700.00 9 409.15 Bituminous Tack Coat Applied 1150 GAL 6.00 6,900.00 10 604.092 Catch Basin Type B1 -C 1 EA 1 5,100.00 5,100.00 11 604.164 Rebuild Catch Basin 2 EA 4,200.00 -8,40-0.00 12 604.167 Alter Catch Basin 7 EA 840.00 5,880.00 13 604.18 Adjust MH and CD to Grade 2 EA 750.00 1,500.00 14 609.21 Curb Type 2 - Concrete 5800 LF 7.35 42 630.00 15 615.07 Loam 200 CY 83.00 16 600.00 16 618.13 Seeding Method No. 1 30 UNIT 16.50 495.00 17 619.12 Mulch 30 UNIT 16.50 495.00 18 627.7114" White Yellow Pavement Line 16460 LF 0.16 2,633.60 19 627.75 White Yellow Pavement Curb Marking 224 SF 1.10 246.40 20 629.05 Hand Labor 10 MH 42.00 420.00 21 631.12 All Purpose Excavator 10 MH 154.00 1,540.00 22 631.172 Turck - Large 10 MH 89.00 890.00 23 652.36 Maintenance of Traffic 1 LS 21 000.00 21 000.00 24 652.38 Flagger 800 MH 17.00 13 600.00 25 659.10 Mobilization 1 LS 23 000.00 23 000.00 Total Project Bi 1 486 319.00