HomeMy WebLinkAbout1988-05-09 88-222 ORDER�o�n .anon 88-222
Item/Subject: Award If Phase II Construction Contract - Downtown
Parking Garage
Responsible Department: Purchasing
Commentary:
Since the bids that were opened on April 19, 1988 were all
over budget Rich & Associates and City staff have reviewed many
possible cost saving measures with the two low bidders in an effort
to reduce the final cost of the building. A preliminary schedule
of Cost reduction possibilities from the two low bidders is attached
along with the bid tabulations The contract award recommendation
from Rich & Associates (copy attached) focuses primarily on the two
methods of construction and the construction schedule. Recmmoende-
ations for all cost saving measures and a final building budget will
be available for the May 9 Council Meeting.
-Manager's Command:
`,'� F'MEm�C {-=AA�aaa��M 11 /µ�Q�ndM
A/,�4 PP. 2rce.n.,,wit,..t-r�±a�'W.✓.v�a.w,9ed.wva�c�
xbAdiessissi�
GAP , 6
-t
1 ll M w`�, cay Alnnnpe.
Associated Information
Budget Approval - 0 qg..5
Legal Approval:
ny sncdrw
Item No.
Page _of_
88-222
Introduced by Councilor Tilley, Hay 9, 1988
ryrypp
CITY OF BANGOR
(TITLE.) @rbrrr, Awarding Contract for Phase II of the Construction of
the Downtown
By the Cily Coaxed ofUle City ofBanpor:
ORDBBSD,
THAT WHEREAS, bids were opened on April 19, 1988 for Phase II
of the construction of the downtown parking garage; and
WHEREAS, all bids w carefully reviewed by City staff and
the City's architectual consultant, Rich & Associates; and
WHEREAS, Rich & Associates and the City staff recommend
and of the construction contract to Reed & Reed Inc., the low
bidder at $4,425,000.00 for the alternate precast construction
design; and
WHEREAS, the City Council Finance Committee has reviewed
this recommendation and have approved the contract award subject to
full Council approval;
NOW, THEREFORE, BE IT ORDERED BY THE CITY COUNCIL OF
THE CITY OF BANGOR THAT Reed & Reed Inc. is hereby awarded the
construction contract in the Amount of $4,425,000.00 for Phase II,
of the downtown parking garage.
STATEMENT OF FAM This contract will provide all required construction
for the completion of the downtown parking garage.
88-222
IN CITY COUNCIL O R D E R
May 9, 1998
Pass d
Title
exxv eRK A.wWU1g .Ganact .f¢c Rhace .LL xC .U1e.
.Sanetivctien.n{,che Dovntn� P.Nck'a .
Garage.
Introduced and filed Ey
Councilman
88-222
Satsiedulee
KING
m
level
rmmet mrmnw
days
BANGOR,
1M07
Q`
mosto
assess
sm Film
3d5
elms Ims d/19/831
CITYROF MAINE
ro t
sq.fe./totare
rete
m
rmmet mrmnw
®
#similarad
Q`
mosto
assess
sm Film
I
elms Ims d/19/831
ro t
1 �eirn
INCURRED
1. 1. J e d
IBMwS
tmutrveelw
8.3]1.693
150
-
m
to
yee ew
a m
eededue do
"
I
ruM W YI-153
•alu uee roep
WA
WA
N.61o.pd
sv.06x,sa
n
es
his
yet
eaM
Mp %-15X
eem t nee
N.95d.Ob
v.5ro.wo
ffi
yd
he
l M,k
"
1m,
N/A
NIA
N.55.w
EL.35o.am
w
VB
v¢
IW wv s ES
yeu num.,,.
enemw wpml®
3/69 (Mid
atato mark V
15X -20x
Mss Wry
µ.07.0Po
59n.0Po
-
-
Te
y6
ffi
ffi
Beae t
ecUbale wH
u IU -M
ee WV
N.J]O.ON
M)
as
ffi
MS
6]U ulmtiv
('wim"d till "blade)
e
dw elm e
dp
See a
lap1t1l
I
��
I
i
i
Ilii
CITY OF BANGOR, MAINE
PROPOSED PARKING STRUCTURE
DEDUCTION COMPARISON
I
1®LI® SIw.000• i 85.[M '_ A3.000••••
i
Olu Gry. s 91.1Yj �. S6. Fjo sid.%E^^
S 95.805 mnl
I -
94475"'
v ooe to
11191"1 told
old of Y.N5.wog
,Mma lov
_ sy.w
wtnynesing.
RICH AND ASSOCIATES, INC.
ARCHITECTURE , PARKING CONSULTANTS • ENGINEERING
35240 LAHSER ROAD , SOUTHFIELD, MICHIGAN 48030
(313) 3535050
May 2, 1988 R1`CF/bepf4,V,
City Of Bangor Maine
City HallyyB
73 Harlow
Bangor, Maine 04401
Attn: Mr. David N. Pellegrino, Purchasing Agent
Be: .Recommendation for Phase II Contract
of the Water Street Parking Structure
Our File No. 8811
Dear Mr. Pellegrino:
Rich and Associates has reviewed the bids as submitted by the
four contracting firma. On Wednesday April20th, Bill Paxton
from Rich and Associates met with both individuals from Reed and
Reed and Diaz Corp. to get clarification on the respective bids
and to also request additional information on adds and deducts
that we saw could be taken for the project.
Though responses from the firms were expected on April 25th, we
did not receive confirmation on dollar amounts via telephone
until April 28th and April 29th. W¢ have reviewed the alternates
proposed for adds and deducts by both organizations and have the
following comments.
1. In philosophy, Rich and Associates prefers the construction
of a precast parking structure over that of poured in place.
This is due to the strict quality control requirements for a
parking structure. It has been our experience as both
designer and owner, that precast offers more assurances for
quality control in the plant and also in the field. In a
poured in place parking structure quality control is of the
utmost concern, this can be a problem depending on the
contractor and the supervision ofthe construction.
Therefore, there is a preference in our firm towards precast
design and building.
UNGTIONUOESIGN • PARKING SECURITY PLANNING
N
OPERATINGSTUDIES , DESIGNSUILD , DEVELOPMENT, FINANCING& PROFESSIONAL PARKING MANAGEMENTMANAGEMENT THROUGH MEOPARK IHC.
Mr. David N. Pellegrino
May 2, 1988
Page 2
As you may remember in October or November when our firm was
completing schematic designs and design development drawings, we
thoroughly interviewed all the precasters within a supply area of
Bangor. Based upon unit coat estimates of the precaster at that
point, we ruled out the precast because the cost per square foot was
between $18.50 and $21 per square foot. With this in mind we priced
out poured in place, post tension construction and found it
significantly cheaper than precast. However, it .is our
understanding that a precaster who had expected several jobs to
materialize found these jobs were cancelled and immediately needed
additional work and therefore offered lower cost in precast.
2. The bids as submitted by Diaz Corp. in both their base bid and
an alternate for a longer time schedule were to the best of our
knowledge, bids based upon the plans and specifications as
developed by Rich and Associates.
The Reed and Reed base bid of a poured in place parking structure to
the best of our knowledge was also bid from our plans and space.
However, the voluntary alternate for precast as submitted by Reed
and Reed did not include a brick exterior on the panels and this did
not appear as an exclusion in their bid form.
We have since requested adds and deducts from both Reed and Reed and
Diaz which are shown on the following chart. However, when we
looked at the Reed and Reed bid, the brick facade desired by the
City was not in the base bid of $4,325,000 and would add $100,000 to
their base bid on the precast design for a total of $4,425,000 as
opposed to the Diaz low bid of $4,370,000. The difference in cost
is approximately $55,000.
RICH AND ASSOCIATES, INC.
Mr. David N. Pellegrino
May 2, 1988
Page 3
3. The time schedules on these two low bids for precast and poured
in place differ greatly, when examined carefully. The Diaz
proposal or bid or $4,370,000 has a substantial completion by
June and a total completion by the end of August. The precast
structure has a substantial completion around December of 1988
and final completion around June of 1989. This latter point i
somewhat confusing in that if the superstructure of the parking
structure is up by December of 1988 all that would remain are
the elevators, elevator shafts and stair towers, which can be
completed during the winter months. Therefore, we feel a June
completion is giving the worse possible scenario to the City
and that the deck could be completed substantially before that.
As a note t0 this point Diaz has told Rich and Associates that they
would be able to give partial occupancy of the structure in December
for the Holiday season. However, Rich and Associates has not
ascertained how they would do this and it is somewhat questionable
if in fact this could be done.
All in all it is the recommendation of Rich and Associates that the
City consider the Reed and Reed bid for precast design of the parking
structure as a viable alternate to the poured in place and that the
City proceed t0 contract with Reed and Reed for the construction of
the parking deck in precast. There are several points that lean
toward this one of which is the obvious benefitsof precast. Also the
fact that Reed and Reed will be doing the pile contract and can
therefore coordinate the project better offers a smoother transition
from foundation site work to superstructure and actual construction.
Finally the time schedule for precast should allow substantial
completion before June of 1989.
RICH AND ASSOCIATED. INC.
Mr. David N. Pellegrino
May 2, 1988
Page 4
There are however, two key points in the decision for Reed and Reed.
The contractor has proposed on precast for which the building has not
been designed. A firm price has been given for this deck based upon a
layout of the precaeter. The final design of the building still
needs to be completed 1£ precast 1e chosen. There is also the
possibility of substantial change orders in this final design that
would not occur with the poured in place scheme.
In order to avoid these potential change orders a clear understanding
of the ground rules with Reed and Reed must be established. 4a'
essence, what we have in choosing Reed and Reed is a negotiated
design build bid in.which Rich and Associates would work for the City.
and with the contractor and redesign the building for precast.
Therefore,r n summary while the poured in place concrete bid is o
paper lowerin overall cost, it is our recommendation that the City
proceed with the precaeter and the precast bid from Reed and Reed,
because of the timescheduleand quality control.
I£ there are any questions on this letter please feel free to contact
the writer.
Sincerely,
RICH AND ASSOCIATES. INC.
ichara A. Ricn
PAR: so
Enclosure
RICH AND ASSOCIATES, INC.